Desktop installation

24
SAN32M-2 Installation and Service Manual
3. If any items are damaged or missing, contact the IBM Quality
Hotline toll-free at 1-800-442-6773 within the United States and
Canada. In other locations direct dial 770-858-8459.
To install a switch on a desktop:
1. Remove the backing from the four adhesive rubber pads and
apply the pads to the underside of the switch. Ensure pads are
aligned with the scribed circles at each corner.
2. Position the switch on a table or desktop as directed by the
customer. Ensure:
— Grounded AC electrical outlets are available.
— Adequate ventilation is present, and areas with excessive heat,
dust, or moisture are avoided.
— All planning considerations are met. Refer to IBM TotalStorage
Products in a SAN Environment - Planning Manual (GC26-7675)
for information.
3. Verify all customer-replaceable units (CRUs) are installed as
ordered.
4. Connect both AC power cords to receptacles at the rear of the
chassis.
5. Connect AC power cords to separate (for redundancy) facility
power sources that provide single-phase, 100 to 240 volt
alternating current (VAC) current.
6. When the first power cord is connected, the switch powers on and
performs power-on self-tests (POSTs). During POSTs:
a. The green power (PWR) LED on the front panel illuminates.
b. The amber system error (ERR) LED on the front panel blinks
momentarily while the switch is tested.
c. The green LED associated with the Ethernet port blinks
momentarily while the port is tested.
d. LEDs associated with Fibre Channel ports blink momentarily
while the ports are tested.
7. After successful POST completion, the PWR LED remains
illuminated and all other front panel LEDs extinguish.