260 Chapter 7 Upgrades, migrations, and feature expansion
Task
Record the current server
configuration from CP1
Run the Upgrade Wizard
on the existing 1005r
server (CP1)
Prepare the new 1005r
server (CP2)
Run the Setup Wizard
on the new 1005r server
(CP2)
Configure CP1 using the
CallPilot Configuration
Wizard
Configure CP2 using the
CallPilot Configuration
Wizard
Complete the High
Availability feature
configuration

Prepare the switch

The switch configuration must be completed before the High Availability
feature can be implemented.
Preparing the switch
Step
1
Copyright © 2007, Nortel Networks
.
Estimated time
5 minutes
160 minutes depending on
system and database size
10 minutes
210 minutes (includes
restore time)
40 minutes
40 minutes
215 minutes
Action
Configure the Meridian 1 or CS 1000 switch.
For detailed information, see the following:
Meridian 1 and CallPilot Server Configuration (NN44200-302)
Communication Server 1000 and CallPilot Server Configuration
(NN44200-312)
Note 1: Both High Availability servers must use the same
Control Directory Number (CDN).
Note 2: Server CP2 requires dedicated MGate cards in the
switch to function correctly. Both the number of MGate cards and
the switch configuration must be the same as for the existing
CallPilot server CP1.
Nortel CallPilot
High Availability: Installation and Configuration
NN44200-311 01.06 Standard
5.0 15 May 2007
Procedures
See
"Recording the current 1005r
server configuration (CP1)" (page
262)
See
"Running the Upgrade Wizard on
CP1" (page 263)
See
"Prepare the new 1005r server
(CP2)" (page 266)
See
"Running the Setup Wizard on
CP2" (page 267)
See
"Configuring CP1 using the
Configuration Wizard" (page 271)
See
"Configuring CP2 using the
Configuration Wizard" (page 275)
See
"Completing the High Availability
feature configuration" (page 279)

Advertisement