Moving from a domain to a workgroup

If the CallPilot 5.0 High Availability system must be moved to a workgroup
(from a domain), use the following procedure to join a workgroup.
Joining a workgroup
Step
This procedure assumes that CP1 is the active server and CP2 is the
standby server.
1
2
3
Copyright © 2007, Nortel Networks
.
Action
On CP1, launch the AutoStart Console and stop monitoring.
For more information, see
monitoring)" (page
213).
Take the CallPilot resource group offline on CP1. For more
information, see
"Taking the CallPilot resource group offline" (page
211).
On CP1, do the following:
a. Right-click My Computer.
Result: The System Properties window appears.
b. Select the Computer Name tab and click Change.
Result: The Computer Name Changes window appears.
Nortel CallPilot
High Availability: Installation and Configuration
NN44200-311 01.06 Standard
5.0 15 May 2007
"Disabling automatic failovers (stop

Advertisement

Table of Contents
loading

Table of Contents