Test the CP PM Call Server
Procedure 21

Testing the CP PM Call Server

1
Verify that the CP PM Call Server is active.
LD 135
STAT CPU
2
Check dial-tone.
3
Verify that the CP PM Call Server is active, redundant, and single.
4
Make internal, external, and network calls.
5
Check attendant console activity.
6
Check IP Peer networking for incoming and outgoing calls.
7
Check applications (CallPilot, Symposium, and so on).
Install the software on the second CP PM Call Server
Procedure 22
Installing the software on the second CP PM Call Server
1
Attach the ELAN and TLAN cables to the CP PM faceplate connectors
between the CP PM Call Servers.
2
Complete procedures 22 through 27 for the second CP PM Call Server.
3
Each CP PM Call Server can be named: CP PM Call Server 1 and CP PM
Call Server 0.
Note: Do not install ELAN and TLAN cables at this time.
Installing software on the CS 1000E
Load program
Get the status of the CPUs
End of Procedure
End of Procedure
Communication Server 1000E
Page 133 of 466
Installation and Commissioning

Advertisement

Table of Contents
loading

This manual is also suitable for:

1000eCommunication server 1000Communication server 1000e

Table of Contents