Chapter 2 Set Up the Rack
Note: 2U of space is reserved above the PDUs for cable routing. The number
and type of PDUs depends on the power supply. If more PDUs are needed, or
when you need to add additional components into the rack (such as adding
another Slammer), then everything has to move up to make room, keeping
the 2U of reserved space, and moving any Bricks displaced at the top to the next
rack.
Note: In a system that is configured for the maximum number of Bricks, connect
the additional racks to the first rack before you install and cable the hardware
components.
Related references
Cabling Practices for the Pillar Axiom 600 System
Related tasks
Rename the Bricks

About Component Placement for One Slammer and FC Bricks

Pillar Axiom 600 systems with one Slammer support up to 15 Fibre Channel (FC)
Bricks.
Install the hardware components in the rack as shown in the following figure. Any
components that are not installed must be replaced with filler panels.
The figure below illustrates how the Pillar Axiom 600 system components are
mapped into a fully loaded 42U rack for the following configuration:
● 1 Pilot
● 1 Slammer
● 15 FC Bricks
About Component Placement