Oracle Pillar Axiom 600 Hardware Installation Manual

Oracle Pillar Axiom 600 Hardware Installation Manual

Oracle pillar axiom 600 hardware installation guide
Hide thumbs Also See for Pillar Axiom 600:
Table of Contents

Advertisement

Quick Links

Pillar Axiom 600
Hardware
Installation Guide

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Pillar Axiom 600 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Oracle Pillar Axiom 600

  • Page 1 Pillar Axiom 600 Hardware Installation Guide...
  • Page 2 Oracle Corporation and its affiliates disclaim any liability for any damages caused by use of this software or hardware in dangerous applications.
  • Page 3 Les informations fournies dans ce document sont susceptibles de modification sans préavis. Par ailleurs, Oracle Corporation ne garantit pas qu’elles soient exemptes d’erreurs et vous invite, le cas échéant, à lui en faire part par écrit.
  • Page 4: Table Of Contents

    Pillar Axiom 600 Series Components........
  • Page 5 About Cabling a Pillar Axiom 600 System........
  • Page 6 About HBA Driver and Firmware Installation (SAN Only)..... . . 140 About Switch Zone for HBA Set Up (SAN Only)......141 Attach the Rack Doors and Panels.
  • Page 7 Brick Packaging and Transportation........205 Pillar Axiom 600 PDU Hardware Specification......206...
  • Page 8 Appendix D Expansion of a Pillar Axiom 600 System Configuration About Expanding a Pillar Axiom 600 Configuration......211 Complete the Brick Pre-Installation Checklist.
  • Page 9 List of Figures Figure 1 Floor plan for rack installation........28 Figure 2 Sample 42U side panels.
  • Page 10 Figure 42 Brick connections in strings........90 Figure 43 Pillar Axiom 600 back-end cabling overview......91 Figure 44 Pilot management cables.
  • Page 11 Figure 50 Sample power cabling scheme with 230V power, 20A PDU....118 Figure 51 Sample power cabling scheme with 115V on a TCP2105-1 PDU... . 119 Figure 52 Sample power cabling scheme with 230V (one circuit shown).
  • Page 12 Table 4 Pillar Axiom 600 series components........
  • Page 13 Table 22 Pillar Axiom 600 electrical requirements......114 Table 23 LEDs on the Slammer bezel........129 Table 24 8 Gb/s FC HBA LED status.
  • Page 14 Table 67 PDU specifications..........206 Table 68 Rack specifications for a Pillar Axiom 600 system..... . . 208 Table 69 Slammer cross connection configuration version 1 PIMs.
  • Page 15: Preface

    Being familiar with certain other technical documentation for Oracle’s Pillar Axiom 600 helps you succeed in the use of this guide. Before you install Oracle’s Pillar Axiom 600 system, you should be familiar with certain basic characteristics of the environment in which you intend to install the...
  • Page 16: How This Guide Is Organized

    How This Guide Is Organized This guide provides procedural and reference information to install the various components within an Oracle Pillar Axiom 600 system, power it on, and perform the initial configuration. To perform any upgrade, you must contact the Pillar World Wide Customer Support Center.
  • Page 17: Table 1 Additional Information Resources For All Systems

    ● Appendix B summarizes all warning and caution notices in various languages. ● Appendix C provides reference information on the hardware specifications for the Oracle Pillar Axiom 600 system and its various components. ● Appendix D provides information on adding additional Bricks to an Oracle Pillar Axiom 600 system and the associated cabling of those Bricks.
  • Page 18: Typographical Conventions

    Axiom 600 systems. Access Documentation Technical documentation (including installation, service, cabling, integration, and administration guides) for Oracle’s Pillar Axiom 600 storage system is available from several sources. Pillar Axiom Log in to your Pillar Axiom system. Navigate to the Support...
  • Page 19: Table 2 Typography To Mark Certain Content

    Preface Table 2 Typography to mark certain content Convention Meaning italics Within normal text, words in italics indicate: ● A reference to a book title. ● New terms and emphasized words. ● Command variables. Indicates one of the following, depending on the context: monospace ●...
  • Page 20 Preface Table 3 Contacts at Pillar Data Systems (continued) For help with... Contact... Have your system serial number ready. support@pillardata.com Pillar Customer Support (http://support- portal.pillardata.com/csportal/login.seam) Training (custom or Training and Education (http://www.pillardata.com/ packaged) support-education/training/) Professional services globalsolutions@pillardata.com and inquiries Global Solutions (http://www.pillardata.com/support/ professional-services/) Sales and general...
  • Page 21: Chapter 1 Before You Begin

    Chapter 1 Before You Begin HAPTER Before You Begin Pillar Axiom 600 Series Components Pillar Axiom 600 systems contain a specific combination of the components listed in the following table: Table 4 Pillar Axiom 600 series components Product name Model and description Brick storage ●...
  • Page 22 Model and description ● PDU 500-3P16A—230V, 16A, IEC; (230/400) Racks ● RACK500-42U—42U cabinet assembly with doors Note: The following Pillar Axiom 600 components continue to be supported but are no longer available for new systems: ● BRX 500-160A7 ● BRX 500-250A7 ●...
  • Page 23: Customer-Supplied Equipment And Tools

    Chapter 1 Before You Begin Customer-Supplied Equipment and Tools Before starting the installation of a Pillar Axiom 600 system, be sure you have the needed equipment and tools installed or available. Table 5 Required tools Tool Purpose Illustration 1/4 inches (7 millimeters) Adjust leveling feet.
  • Page 24: Table 6 Required Equipment And Supplies

    On hand? Item Purpose At least two power sources on Provide power to the PDUs. independent circuits with Pillar Axiom 600 systems appropriate connectors for the require redundant power voltage and amperage ratings supplies from two PDUs on separate input circuits.
  • Page 25: Safety Notice Conventions

    Important! To emphasize a point, to remind you of something, or to indicate potential problems in the outcome of the in-process task. A set of important safety notices apply throughout this guide. Read them before working on a Pillar Axiom 600 system. Related concepts Safety Statements •...
  • Page 26: Chapter 2 Set Up The Rack

    Set Up the Rack About Component Inspection Each Pillar Axiom 600 system is built to a customer's specifications and shipped in a single shipment. Check the components you received against the packing slip (or bill of lading), which lists everything that was shipped. If any components are missing, call 1-877-4PILLAR (474-5527) and report what was not included in your shipment.
  • Page 27 Axiom 600 system. Additionally, be sure the non-Pillar rack has square mounting holes in the vertical channels. Round mounting holes are not acceptable. Illustrations show a Pillar Axiom 600 42U rack or parts of it. If you have a non- Pillar rack, it should be similar.
  • Page 28: Rack Position

    Chapter 2 Set Up the Rack Rack Position The following figure illustrates a floor plan for new rack installations. The space around the rack (or bay, if you have multiple racks) is needed to perform the installation tasks safely. Figure 1 Floor plan for rack installation Legend 1 Back of unit 2 60 inches (152 centimeters)
  • Page 29: Figure 2 Sample 42U Side Panels

    Chapter 2 Set Up the Rack Prepare the Racks To create a bay of Pillar racks, first remove the adjacent (inner) side panels from each rack (see the following figure) and move the racks into position. You will route the cables directly from one rack to the other through the open sides of the racks because the cables are not long enough to route through a raised floor.
  • Page 30: Figure 3 Location Of Frame Corners

    Chapter 2 Set Up the Rack 4 Position the racks so that their open sides abut and their front sides are flush. Attach the Connection Bracket The connection bracket provides extra rigidity to the bay. Important! Make sure that at least one of the racks is not anchored so you can adjust its position while you attach them together.
  • Page 31: Figure 4 Connection Bracket Installation

    Chapter 2 Set Up the Rack Figure 4 Connection bracket installation Legend 1 Frames 2 Baying connection bracket 3 M8 hex screws 3 Insert an M8 hex screw through the hole in one of the bracket corners. 4 Loosely screw the M8 screw into the threaded hole in the frame. 5 Insert an M8 hex screw through one of the other corner holes in the bracket and loosely screw it into the threaded hole in the frame.
  • Page 32: Figure 5 Roof Baying Plate Attachment

    Chapter 2 Set Up the Rack 1 At the front of each rack roof, use a T30 Torx® screwdriver to remove the two adjacent Torx-head screws and set them aside. 2 Place a baying plate over the two holes. Figure 5 Roof baying plate attachment Legend 1 Roof baying plates 2 M12 Torx screws...
  • Page 33: Adjust The Leveling Legs

    Chapter 2 Set Up the Rack Figure 6 Adjacent anchor bolts at the front of the racks Legend 1 Anchor bolts 7 Hold the baying plate across the two anchor-bolt holes and loosely replace the anchor bolts. 8 Repeat Steps 6 and 7 in the back of the racks. 9 Use the socket wrench to tighten the connection bracket screws.
  • Page 34: Figure 7 Rack Leveling Leg Locations

    Chapter 2 Set Up the Rack 1 Turn each leveling leg clockwise to lower the feet until they touch the floor. Use a 1/4-inches (7-millimeters) flat-tip screwdriver in the slot at the top of the leg. Figure 7 Rack leveling leg locations Legend 1 Caster brackets 2 Leveling legs are pre-installed in each caster bracket.
  • Page 35: About Rack Stability

    Chapter 2 Set Up the Rack Note: If you connect racks in a bay it is more important that the racks be at the same height than level so that you can bolt them together. About Rack Stability After you move the rack to its final position and adjust the legs, you must stabilize it to keep it from shifting when you install the components.
  • Page 36: Figure 9 Attach Anchor Bolts To Rack

    Chapter 2 Set Up the Rack Install the Anti-Tip Brackets 1 Screw the anchor bolt into the bottom outside corner of the rack frame until the bolt is seated. Figure 9 Attach anchor bolts to rack 2 Slide the bracket fingers into the anchor bolt pocket as illustrated in the following figure.
  • Page 37: Figure 11 Secure Anti-Tip Brackets To The Floor

    Chapter 2 Set Up the Rack 3 Position the anti-tip bracket so that it points away from the rack and is parallel to the sides. 4 Adjust the anchor bolt so that it is finger-tight against the anti-tip bracket, and secure the anti-tip bracket to the floor. Figure 11 Secure anti-tip brackets to the floor 5 Repeat Step 1 through Step 4 for all four corners.
  • Page 38: Figure 12 Stabilizer Plate Attached To The Rack Base And Floor

    Chapter 2 Set Up the Rack 2 While adjusting the leveling legs to raise or lower the rack, align the holes in the short side with the holes in the rack frame. 3 Insert an M8 bolt into each hole in the short side of the stabilizer plate. 4 Use the hex wrench to tightly bolt the stabilizer plate to the rack.
  • Page 39: About Component Placement

    If you are building a rack that only contains Bricks, you should still start from the bottom. Note: The physical location of the components in the Pillar Axiom 600 rack can vary if the system is installed in the field. Always check the cables at the back of the rack to validate the physical location of each Brick.
  • Page 40: Table 7 Configuration Limits For A Pillar Axiom 600 System

    Bricks in the Pillar Axiom 600 system. The maximum number of a specific Brick (SATA, FC, or SSD) allowed in the Pillar Axiom 600 system also depends on the number of Slammers in the system.
  • Page 41: About Component Placement For One Slammer And Sata Bricks

    ● For a mix of SSD and SATA Bricks: 2 SATA + 1 SSD or 2 SSD + 1 SATA. Pillar Axiom 600 systems support up to 32 FC Bricks, or 64 SATA Bricks, or 32 SSD Bricks or any combination of these three types, provided there are no more than 64 total Bricks, 32 FC Bricks or 32 SSD Bricks in the system.
  • Page 42: Figure 13 42U Racks Containing One Slammer And Up To 32 Sata Bricks

    Filler panels should be mounted on the front rails to fill any spaces below the Pilot or the lowest Pillar Axiom 600 component in the rack. Single Phase PDUs are mounted on the rear rails so that there are filler panels in the front.
  • Page 43: About Component Placement For One Slammer And Fc Bricks

    Rename the Bricks • About Component Placement for One Slammer and FC Bricks Pillar Axiom 600 systems with one Slammer support up to 15 Fibre Channel (FC) Bricks. Install the hardware components in the rack as shown in the following figure. Any components that are not installed must be replaced with filler panels.
  • Page 44: Figure 14 Fully Loaded 42U Rack For One Slammer And 15 Fc Bricks

    Filler panels should be mounted on the front rails to fill any spaces below the Pilot or the lowest Pillar Axiom 600 component in the rack. Single Phase PDUs are mounted on the rear rails so that there are filler panels in the front.
  • Page 45: About Component Placement For Two Or Three Slammers And Fc Bricks

    • About Component Placement for Two or Three Slammers and FC Bricks Pillar Axiom 600 systems with two or three Slammers support up to 32 FC Bricks. Note: This topic applies only to Pillar Axiom 600 systems. Install the hardware components in the rack as shown in the following figure. This...
  • Page 46: Figure 15 Fully Loaded 42U Racks For Three Slammers And 32 Fc Bricks

    Filler panels should be mounted on the front rails to fill any spaces below the Pilot or the lowest Pillar Axiom 600 component in the rack. Single Phase PDUs are mounted on the rear rails so that there are filler panels in the front.
  • Page 47: About Component Placement For Four Slammers And 64 Bricks

    • About Component Placement for Four Slammers and 64 Bricks Pillar Axiom 600 systems with four Slammers support up to 64 Serial ATA (SATA) Bricks, or a combination of up to 32 FC Bricks and 32 SATA Bricks in a mixed system.
  • Page 48: Figure 16 Fully Loaded 42U Racks For Four Slammers And 64 Bricks

    Chapter 2 Set Up the Rack Figure 16 Fully loaded 42U racks for four Slammers and 64 Bricks Important! In the above configuration, make sure Fiber Channel (FC) and serial ATA (SATA) Bricks are loaded in the cabinet so that the power load on the PDU is correct.
  • Page 49: Pilot Rail Kit Parts

    Related concepts About Component Placement for Two or Three Slammers and FC Bricks • Related references Cabling Practices for the Pillar Axiom 600 System • Related tasks Rename the Bricks • Pilot Rail Kit Parts Verify that the rail kit contains all the parts listed in the table.
  • Page 50: Install A Pair Of Pilot Mounting Rails

    Chapter 2 Set Up the Rack Table 9 Pilot rail kit parts (continued) Component Drawing (not to scale) Quantity 10-32 Hex nuts for Eight attaching scopes to rails 2500-01051-xx Rack mount spacers Four 2500-01065-xx Rack mount nut bar 2526-00106-xx 10-32 x 1/2 inch Torx head (#20) screws 2500-01071-xx Install a Pair of Pilot Mounting Rails...
  • Page 51: Figure 17 Scope Hook Attachment

    Chapter 2 Set Up the Rack Figure 17 Scope hook attachment Legend 1 Vertical rail at back of rack 2 Rack unit (RU) 32 3 Scope hook 4 Bottom holes for each unit 5 RU 31 In the preceding figure, two labeled rack units, 31 and 32, are shown at the back of the rack.
  • Page 52: Figure 18 Positioning Spacer Bar

    Chapter 2 Set Up the Rack 3 While keeping the rail horizontal, fit the four-hole spacer bar into the four square rack holes that span the boundary between the two units that this rail is to occupy. The following figure shows positioning a spacer for units 35 and 36. Figure 18 Positioning spacer bar Legend 1 Rack unit boundary...
  • Page 53: Slammer Rail Kit Parts

    Chapter 2 Set Up the Rack Figure 19 Pilot rail front attachment Legend 1 Back 2 Four-hole spacer bars 3 Front 4 Slider lock nuts 4 Use two 10-32 Torx Washer Head screws to secure the rail through the rack into the two center holes in the spacer bar. The top and bottom holes are use to secure the Pilot control units to the rack.
  • Page 54: Table 10 Slammer Rail Kit Parts

    Chapter 2 Set Up the Rack To install a pair of Slammer rails, you need: ● One Slammer rack rail kit with rails and scopes pre-attached ● #20 Torx wrench ● Socket wrench Slammer rails are 4U rack rail assemblies that contain the following parts: Table 10 Slammer rail kit parts Component Drawing (not to scale)
  • Page 55: Install A Pair Of Slammer Mounting Rails

    Chapter 2 Set Up the Rack Install a Pair of Slammer Mounting Rails 1 Hang the scope hook in the appropriate hole at the back of the rack, as shown below. These rail scopes are always used for components that take up at least two rack units.
  • Page 56: Figure 21 Slammer Rails Installed In Rack

    Chapter 2 Set Up the Rack ● When you place the hook in the middle of unit 32, the bottom of the rail lines up with the bottom of unit 31. ● A 4 U Slammer rail would fill units 31-34 in the above illustration. 2 At the front of the rack, slide the rail scopes until the rail reaches the holes at the front.
  • Page 57: Brick Rail Kit Parts

    Chapter 2 Set Up the Rack Brick Rail Kit Parts Verify that the rail kit contains all the parts listed in the table below. To install a pair of 2U rack rails, you need: ● One Brick rail kit with rails and scopes pre-attached ●...
  • Page 58: Install A Pair Of Brick Mounting Rails

    Chapter 2 Set Up the Rack Table 11 Brick rail kit parts (continued) Component Drawing (not to scale) Quantity 10-32 x 1/2 inch Torx head (#20) screws 2500-01071-xx Related tasks Install a Pair of Brick Mounting Rails • Install a Pair of Brick Mounting Rails 1 Hang the scope hook in the appropriate hole at the back of the rack, as shown below.
  • Page 59: Figure 22 Scope Hook Attachment

    Chapter 2 Set Up the Rack Figure 22 Scope hook attachment Legend 1 Vertical rail at back of rack 2 Rack unit 32 3 Scope hook 4 Bottom holes for each unit 5 Rack unit 31 In the preceding figure, two labeled rack units, 31 and 32, are shown at the back of the rack.
  • Page 60: Figure 23 2U Rack Rails Installed In Rack

    Chapter 2 Set Up the Rack See the next figure. Repeat this step for the other center screw in the front and for the screws at the back, under the scope hook. The square hole in the front is at the top on the left side and at the bottom on the right side.
  • Page 61: Chapter 3 Install Components

    Pillar Axiom Site Preparation Survey and in the hardware specifications appendix. Important! If the external power supplied to the Pillar Axiom 600 is 208V instead of 230V, the number of components that can be powered by a single PDU is reduced.
  • Page 62: Install A 1U Pdu

    Figure 24 Snap-in cage nut ● For round mounting holes, clip one 10-32 clip-on cage nut into the bottom and 3rd holes of each channel in the pair. (Pillar Axiom 600 systems are not shipped with clip-on cage nuts.) 2 Insert the PDU into the rack, as shown below.
  • Page 63: Figure 25 Securing A 1U Pdu In The Bottom Of A Rack

    Chapter 3 Install Components Figure 25 Securing a 1U PDU in the bottom of a rack Note: This image is for illustration purposes only. Your hardware component might look different. 3 Align the ears of the PDU to the four cage nuts. 4 Insert a 10-32 x 1/2 inch screw through the top and bottom holes in the right and left ears of the PDU and into the cage nuts.
  • Page 64: Install A 2U Pdu

    Chapter 3 Install Components 6 Repeat this procedure to install any other 1U PDUs. Install a 2U PDU 1 Depending on the type of rack mounting holes, choose one of: ● For square mounting holes, snap a 10-32 snap-in cage nut into the bottom and seventh hole of each vertical rail.
  • Page 65 Chapter 3 Install Components Note: This image is for illustration purposes only. Your hardware component might look different. 3 Insert a 10-32 x 1/2 inch screw through the bottom hole in the right and left ears of the PDU and into the cage nuts. Secure both screws tightly. 4 Repeat Step 3 for the top holes in both ears.
  • Page 66: Install A Pilot Management Controller

    Chapter 3 Install Components Install a Pilot Management Controller Installation of the Pilot control units at the bottom of the rack, just above the power distribution units (PDUs), is efficient and makes future expansion as easy as possible. Required tools: ●...
  • Page 67: Figure 29 Insertion Of The Upper Pilot Cu

    Chapter 3 Install Components Figure 29 Insertion of the upper Pilot CU Note: This image is for illustration purposes only. Your hardware component might look different. 4 Use a 10-32 Torx screw through the hole in each Pilot CU ear and tighten the screw securely using a #20 Torx wrench.
  • Page 68: Pilot Versions

    Chapter 3 Install Components Pilot Versions There are several versions of Pilot control units (CUs) available. Figure 30 Figure 34 illustrate the different versions of the Pilot: Figure 30 Pilot CU (1450–00259–XX) (Back view) Legend 1 Serial port 2 USB flash memory drive inserted into the lower USB port 3 Ethernet ports 4 Management port Pilot Versions...
  • Page 69: Figure 31 Pilot Cu (1450-00179-Xx) (Back View)

    Chapter 3 Install Components Figure 31 Pilot CU (1450–00179–XX) (Back view) Legend 1 Pilot power switch 4 Management port 2 Ethernet port (ETH1) 5 USB port 3 Ethernet port (ETH0) Figure 32 Pilot CU (1450–00164–XX) Intel Legend 1 Back view of a Pilot CU 4 USB port 2 Front view of a Pilot CU 5 Ethernet port (ETH0)
  • Page 70: Figure 33 Pilot Cu (1450-00170-Xx) Msi, Non-Rohs

    Chapter 3 Install Components Figure 33 Pilot CU (1450–00170–XX) MSI, non-RoHS Legend 1 Back view of a Pilot CU 4 Ethernet port (ETH1) 2 USB port 5 Management port 3 Ethernet port (ETH0) 6 Front view of a Pilot CU Figure 34 Pilot CU (1450-00268-XX and 1030-00005-XX) Legend 1 Back view of a Pilot CU...
  • Page 71: Install A Slammer Storage Controller

    Chapter 3 Install Components Install a Slammer Storage Controller Install the Slammers above the Pilot near the bottom of the rack. Required tools: ● Torx T20 screw driver ● Antistatic wrist strap A Slammer weighs 94 pounds (42.6 kilograms). For safe Caution handling, use two people to lift it.
  • Page 72: Figure 35 Insertion Of A Slammer

    6 Repeat Steps 3 through 5 for the right side of the Slammer. 7 (Pillar Axiom 600 systems only) If you have a two, three, or four Slammer system, install the remaining Slammers now. Important! Do not apply power to the Slammers until instructed to do so.
  • Page 73: Install The Slammer Batteries

    Chapter 3 Install Components Install the Slammer Batteries Slammer batteries are shipped separately. Install Before Date on the Slammer batteries have not expired. 1 Ensure the Install Before Date is printed on the label on top of the battery. If a Install Before Date , contact the Pillar World Wide battery is past the Customer Support Center.
  • Page 74: Figure 37 Slammer Battery Insertion

    Chapter 3 Install Components Figure 37 Slammer battery insertion Note: This image is for illustration purposes only. Your hardware component might look different. Install the Slammer Batteries...
  • Page 75: Install A Brick Storage Enclosure

    Required tool: Torx T20 screw driver, tie wraps, and velcro ties. Note: Brick storage enclosures are packaged and shipped separately from the Pillar Axiom 600 system. 1 Put on an antistatic wrist strap, ground strap, or heel strap and attach the grounding wire to ground.
  • Page 76: Figure 39 Brick Ears

    Chapter 3 Install Components 3 Use two 10-32 Torx screws (one on each side) and a Torx T20 driver to secure the Brick ears to the rack. Important! Use care as you install the screws on the right to avoid damaging the printed circuit, which provides power and signals to the Brick bezel.
  • Page 77 9 When connecting the color coded Wye power cables, ensure that each Brick gets a power feed from two separate PDUs. 10 Connect the FC cables as indicated in the wiring diagrams included in the Pillar Axiom 600 SSF Cabling Reference and power on the Bricks. Related concepts About Power Cabling •...
  • Page 78: Set The Identity Of Bricks

    Chapter 3 Install Components Set the Identity of Bricks 1 Locate the digital push button at the top of the face of the Enclosure Services (ES) module. This figure identifies the location of the digital push button, which is used to set the Brick ID.
  • Page 79 0. The digit setting for the FC Expansion Brick is pre-set to 1. However, the digit setting must always be verified during installation. Otherwise, the Pillar Axiom 600 system cannot bring the Brick online. 3 If the digit setting is not set correctly, push the button using a sharp object, such as the end of a paper clip or a small screwdriver to set the Brick ID.
  • Page 80: Replace A Brick Storage Enclosure

    Important! Before making a Storage Domain primary or migrating data to a new Storage Domain, add all the Bricks to the new Storage Domain. Failure to do so may cause performance issues because the Pillar Axiom 600 system might not be able to stripe the data across the appropriate number of Bricks for the Quality of Service (QoS) and Storage Class.
  • Page 81: Delete All Clone Luns

    11 Verify all storage and make sure that all the volumes are online before disconnecting and removing the old Bricks from the system configuration. Note: The Pillar Axiom 600 system does not allow Bricks to be removed if any resources are allocated on that Brick. If there are problems while removing the Bricks, contact the Pillar World Wide Customer Support Center for assistance.
  • Page 82: Accept A Brick

    ● The Pillar Axiom system is in a Normal state. ● The Brick has been cabled correctly according to the wiring diagrams in the Pillar Axiom 600 SSF Cabling Reference . ● Both RAID controllers of the Brick have been powered on.
  • Page 83: Create A Storage Domain

    Chapter 3 Install Components This list is active only when additional Storage Domains exist. 4 (Optional) Replace the default logical name for this newly added Brick with a name of your own choosing. 5 To accept the Brick into the system, click OK. Result: While the Brick is being integrated into the system, the status of the Brick changes from red to yellow to green.
  • Page 84: About Adding Bricks To A Storage Domain

    Chapter 3 Install Components scenario, you can create the new domain without any Bricks with the purpose of assigning the Bricks later. In the above scenario, if you are replacing Bricks in the current primary Storage at least two Bricks of Domain, for the new domain, we recommend that you have the same Storage Class, in the following order of preference: ●...
  • Page 85: Table 12 Effect Of Storage Domains On Brick Additions

    Chapter 3 Install Components Table 12 Effect of Storage Domains on Brick additions Impact administrator defined Storage Domains exist? The system checks the system serial number (SSN) of the Brick to verify whether the SSN is applicable to this Pillar Axiom system.
  • Page 86: Set A Storage Domain As The Primary

    Chapter 3 Install Components Set a Storage Domain as the Primary Circumstances can arise in which you might want to transfer the Persistence VLUN, which contains the system configuration data, from the current primary Storage Domain to a different domain. Prerequisites: ●...
  • Page 87: Move A Volume To Another Storage Domain

    Chapter 3 Install Components Important! After promoting a non-primary Storage Domain to primary, you should verify that the volume named PERSISTENCE has been moved to the Bricks in the new primary domain. To verify proper migration, use the axiomcli storage_allocation command provided by the Pillar Axiom CLI application. When executing this command, include the -brick and -list options.
  • Page 88 Chapter 3 Install Components ○ The target domain does not contain any Bricks in the appropriate Storage Class. To resolve, add to the target domain one or more Bricks of the appropriate Storage Class. ○ The target domain has insufficient free capacity in the corresponding Storage Class.
  • Page 89: Chapter 4 Connect Data Cables

    Connect Data Cables About Cabling a Pillar Axiom 600 System The Pillar Axiom 600 system is a scalable storage system that consists of a Pilot management controller, at least one Slammer storage controller, and some number of Brick storage enclosures depending upon your system model.
  • Page 90: Figure 42 Brick Connections In Strings

    1 Brick connections to Slammer or to Bricks higher in the string 2 Brick connections to other Bricks lower in the string Figure 43 provides a symbolic illustration of the back-end cabling in a sample Pillar Axiom 600 system. About Cabling a Pillar Axiom 600 System...
  • Page 91: Figure 43 Pillar Axiom 600 Back-End Cabling Overview

    Chapter 4 Connect Data Cables Figure 43 Pillar Axiom 600 back-end cabling overview Legend 1 Pilot 2 Slammers 3 Bricks 4 PMI cabling among the Pilot and Slammers 5 SSF cabling among the Slammers and Bricks 6 Brick strings, in which Bricks are connected to each other and the Brick at the...
  • Page 92: Cable Handling Tips

    Chapter 4 Connect Data Cables Cable Handling Tips High speed data optic cables are delicate and can easily be damaged. The cable plug ends and connectors are also sensitive to dirt and contaminants. Follow these tips when handling cables. ● Do not bend the cables beyond its minimum bend radius (MBR). MBR is the tightest bend that the cable can safely tolerate during or after installation.
  • Page 93 Chapter 4 Connect Data Cables ● Support Fiber Channel (FC) cables such that they are not supported by their connectors. ● Do not plug the high-speed serial data cables (HSSDC) into the small form factor pluggable (SFP) ports. Do not plug the SFP cables or transceivers to the HSSDC ports.
  • Page 94: Clean Fiber Optic Cables

    Chapter 4 Connect Data Cables Clean Fiber Optic Cables Follow these tips to clean fiber optic cables. ● Keep the end caps of the plugs installed whenever the plug is not installed. ● Have a fiber optic cable cleaning kit available while handling fiber optic cables.
  • Page 95: Cabling Practices For The Pillar Axiom 600 System

    Cabling Practices for the Pillar Axiom 600 System Follow these fundamental rules and guidelines for cabling Fiber Channel (FC), Serial ATA (SATA), and Solid State Drive (SSD) Bricks in a Pillar Axiom 600 system. All cabling rules and guidelines are categorized into three categories based on the Pillar Axiom 600 system used.
  • Page 96: Table 14 Cabling Principles (System Size Related Issues)

    Table 14: Cabling principles (system size related issues) defines the influence of system size or configuration on the cabling of the Pillar Axiom 600 system. Table 14 Cabling principles (system size related issues) Cabling principle...
  • Page 97: Table 15 Cabling Principles (Slammer Connection Issues)

    Table 14 Cabling principles (system size related issues) (continued) Cabling principle Applicability In Pillar Axiom 600 systems with two Slammers, the Brick at the head of the string must be connected to Slammer 1 and Slammer In Pillar Axiom 600 systems with three Slammers, the Bricks at the head of the string must be connected to Slammer 1 or Slammer 3, and to Slammer 2.
  • Page 98: Table 16 Cabling Principles (Brick Connection Issues)

    CU1 to CU0. Only these links may be optical when the rest of the system is connected with copper cables. Table 16: Cabling principles (Brick connection issues) defines the principles pertinent to connecting Bricks within a Pillar Axiom 600 system. Table 16 Cabling principles (Brick connection issues) Cabling principle Applicability Each Brick in the Brick string connects to the previous Brick in the string.
  • Page 99: Table 17 Cabling Principles (Mixing Brick Types)

    Table 17: Cabling principles (Mixing Brick types) defines the principles that must be followed when mixing Brick types in strings within a Pillar Axiom 600 system. Table 17 Cabling principles (Mixing Brick types) Cabling principle Applicability Brick strings may contain combinations of FC RAID Bricks, FC Expansion Bricks, SATA Bricks (version 2), and SSD Bricks.
  • Page 100: Table 18 Cabling Principles (Fc Expansion Bricks)

    Pillar Axiom 600 SSF Cabling Reference. . information, see Table 19: Cabling principles (Brick order in strings) defines the order in which different Bricks are placed in the string within a Pillar Axiom 600 system. Table 19 Cabling principles (Brick order in strings) Cabling principle Applicability The functionality or performance of Bricks is not affected by their relative position in a Brick string.
  • Page 101: Table 20 Cabling Principles (Brick Balance In Strings)

    Brick types overrides load factor considerations on Brick strings. Table 21: Cabling principles (Brick adds on strings) defines the procedures to be followed when adding Bricks on Brick strings within a Pillar Axiom 600 system. Table 21 Cabling principles (Brick adds on strings) Cabling principle Applicability...
  • Page 102 Recommended method for a non-disruptive Brick add: FIELD Cable all the new Bricks to the Pillar Axiom 600 system without powering them on. Then, power on the Bricks at the rate of one or two at a time.
  • Page 103 Add the new Bricks to the rack along with the crossover cables. Power on the Bricks and wait for the Bricks to initialize. Connect the Bricks to the Pillar Axiom 600 system, one Brick at a time. The Brick type and the Brick model number must both be...
  • Page 104: About Cable Connections Between Two Racks

    Chapter 4 Connect Data Cables About Cable Connections Between Two Racks Note: This topic applies only to Pillar Axiom 600 systems. Be sure the two racks are bayed before you make connections between them. Route the FC cables directly from one rack to the other through the open sides.
  • Page 105: About Cabling The Ssf And Pmi

    Pilot and the Slammers to support management traffic. The SSF operates at 2 Gb/s (copper) or 4 Gb/s (optical) depending on the hardware that is configured on the Pillar Axiom 600 system and on the cables and connectors that are used.
  • Page 106 SSF is configured to run at 4 Gb/s. If such an SFP is inserted into a fabric port, the system disables the port, even after a restart of the Pillar Axiom 600 system. Note: If the SSF is being configured for 4 Gb/s operation, the SFP modules must be installed prior to connecting the optical cables.
  • Page 107: About Jumbo Frames

    To implement jumbo frames, be sure that all Ethernet network interface cards (NICs) in all systems, Ethernet switches, local router interfaces, and all other network devices on the same local networks as the Pillar Axiom 600 system are capable of supporting jumbo frames and are configured for the same effective maximum transmission unit (MTU).
  • Page 108: Connect The Pilot To Your Management Lan

    XML, the network configuration must permit the SAN host to reach the Pilot management IP Ethernet interfaces on port 26004. The Pillar Axiom 600 system is shipped with the following default IP addresses and settings, with the Dynamic Host Configuration Protocol (DHCP) disabled: ●...
  • Page 109: Figure 44 Pilot Management Cables

    7 For Pilot CU0–PLT-0 (the top CU), connect the MGMT port to the Ethernet LAN that is used for managing the Pillar Axiom 600 system. Figure 44 Pilot management cables Note: This image is for illustration purposes only.
  • Page 110: Connect The Pilot Cus

    Chapter 4 Connect Data Cables Connect the Pilot CUs Connect the two control units (CUs) of the Pilot to each other to ensure a heartbeat. Prerequisites: ● One serial null modem cable ● One 0.5 meter Cat 5e Ethernet cable 1 Connect one end of the serial null modem cable to the bottom Serial port of the Pilot CU 0 (the top CU).
  • Page 111 Chapter 4 Connect Data Cables 2 Connect one end of the Ethernet cable to the Ethernet port (ETH0) of the Pilot CU0 (the top CU). Connect the other end of the Ethernet cable to the Pillar Ethernet port (ETH0) of the Pilot CU1 (the bottom CU). Refer to the Axiom SSF Cabling Reference for more information.
  • Page 112: Connect A Slammer To The Data Network

    Chapter 4 Connect Data Cables Connect a Slammer to the Data Network Prerequisites: ● NAS data paths require 1 gigabit Ethernet (GbE) or 10 GbE connections. Both fiber and copper connections are supported. ○ For optical connections: The 1 GbE connections require Pillar supplied 1 GbE small form-factor pluggable (SFP) modules and the 10 GbE connections require Pillar supplied 10 GbE SFP Plus modules.
  • Page 113 Chapter 4 Connect Data Cables 1 For SAN Slammers, connect FC cables from the network interface module (NIM) ports on the Slammer to any open data ports available on two separate FC network switches. 2 For NAS Slammers, connect a gigabit Ethernet (GbE) cable or a 10 gigabit Ethernet (GbE) cable from each NIM port to an open data port on a separate network switch.
  • Page 114: Chapter 5 Connect Power Cables

    Connect Power Cables Component Power Usage The Pillar Axiom 600 system components must be plugged into the PDUs such that they do not exceed the amperage rating of any outlet group. If you exceed the amperage rating, the circuit breakers trip.
  • Page 115: Pdu Outlet Amperage Limits

    Chapter 5 Connect Power Cables PDU Outlet Amperage Limits The number of Pillar Axiom 600 system components you can plug into each Pillar- supplied power distribution unit (PDU) varies. The Pulizzi TPC2105 shown in the following figure can use 115V, 208V, or 230V, 30A (32A in Europe) electrical service.
  • Page 116: Figure 48 Pulizzi Tpc2104 Outlet Amperage Limits

    Chapter 5 Connect Power Cables Figure 48 Pulizzi TPC2104 outlet amperage limits Legend 1 Front 5 Supports 10A 2 Back 6 Supports 10A 3 Supports 115V, 208V, or 230V 7 Supports 10A 4 Supports 10A 8 Supports 16A maximum across all outlets The Pulizzi PC3365 shown in the following figure requires 230/400 VAC WYE three- phase input power.
  • Page 117: About Power Cabling

    Chapter 5 Connect Power Cables About Power Cabling Pillar Axiom 600 racks come with the Brick power cords or Wye power cables pre- installed in the rack with colored tie wraps. These Wye power cables are ready to be plugged into the back of each Brick.
  • Page 118: Figure 50 Sample Power Cabling Scheme With 230V Power, 20A Pdu

    Chapter 5 Connect Power Cables Figure 50 Sample power cabling scheme with 230V power, 20A PDU Legend 1 Brick 1 4 Slammer with two control units 2 Brick 2 5 Pilot 3 Brick 3 6 PDUs Note: This image is for illustration purposes only. Your hardware component might look different.
  • Page 119: Figure 51 Sample Power Cabling Scheme With 115V On A Tcp2105-1 Pdu

    Chapter 5 Connect Power Cables to the quad with the Slammer and the Pilot, so that the load for the middle quad with two Bricks and one Slammer is 8.22A. The load on the right quad with one Slammer, one Brick, and one Pilot is 5.99A. You can distribute the plugs as shown in the following figure: Figure 51 Sample power cabling scheme with 115V on a TCP2105-1 PDU Legend...
  • Page 120: Sample Power Cabling For One Slammer And 16 Sata Bricks

    • Sample Power Cabling for One Slammer and 16 SATA Bricks Note: This topic applies only to Pillar Axiom 600 systems. One Slammer and 16 SATA Bricks (and a Pilot) represent a fully-loaded 42U rack. Split power cables (the plug end splits into two outlet ends) enable you to connect two components to a single outlet in the PDU and reduce the density of the cabling.
  • Page 121: Figure 52 Sample Power Cabling Scheme With 230V (One Circuit Shown)

    Chapter 5 Connect Power Cables Figure 52 Sample power cabling scheme with 230V (one circuit shown) Legend 1–16 (Brick 16 through Brick 1): SATA, 1.18A drawn 21 Total 7.08A drawn 17 Slammer CU 0: 1.275A drawn 22 Total 7.08A drawn 18 Slammer CU 1: 1.275A drawn 23 Total 3.145A drawn 19 Pilot: 0.60A drawn...
  • Page 122: Figure 53 Sample Power Cabling Scheme With Two 208V Single Phase Pdu

    24 Total 3.16A drawn 19 Pilot: 0.66A drawn 25 Total 3.16A drawn 20 Total 3.16A drawn 26. Total 6.32A 21 Total 6.32A drawn 27 Grand Total 12.64A Related references Cabling Practices for the Pillar Axiom 600 System • About Power Cabling...
  • Page 123: Connect Power Cables

    Chapter 5 Connect Power Cables Connect Power Cables When you ordered your Pillar Axiom 600 system, you specified the type of service outlets (in terms of voltage, amperage, and phases) that you have at your facility. The plugs on the power distribution units (PDUs) that you ordered match that service.
  • Page 124 Chapter 5 Connect Power Cables Related concepts Component Power Usage • About Power Cabling • Related references PDU Outlet Amperage Limits • Related tasks Power On the System • Connect Power Cables...
  • Page 125: Chapter 6 Complete The Installation

    Chapter 6 Complete the Installation HAPTER Complete the Installation Power On the System As part of your site planning, you set up a separate circuit and power outlet for each PDU. These outlets should be located within reach of the 15 ft (4.57 m) PDU power input cables.
  • Page 126: Figure 55 Turn On Brick Power

    Chapter 6 Complete the Installation 4 Verify that the digit setting is set correctly for the Brick before powering on the Brick. 5 At the back of the system, turn on the power switches for each Brick. Figure 55 Turn on Brick power Legend 1 Brick power switches Note: This image is for illustration purposes only.
  • Page 127: Figure 57 Turn On Pdu Power

    Chapter 6 Complete the Installation 7 At the front of the system, switch on the PDU circuit breakers to apply power to the hardware components. Figure 57 Turn on PDU power Note: This image is for illustration purposes only. Your hardware component might look different.
  • Page 128: Verify The Front Status Leds

    Chapter 6 Complete the Installation Verify the Front Status LEDs You can verify the installation of the hardware by checking the LEDs on the Pilot, Slammer, and Brick bezels. 1 Verify the Pilot CU LEDs are steady green and not blinking. If the LEDs are off, ensure that the PDU circuit breakers are receiving power and that you have turned them on within a 10 second period of time.
  • Page 129: Figure 59 Dc Power Switch At The Back Of The Pilot

    Chapter 6 Complete the Installation Figure 59 DC power switch at the back of the Pilot Legend 1 Pilot power switch 2 Ethernet ports Note: This image is for illustration purposes only. Your hardware component might look different. 3 Verify that the Slammer STATUS LEDs are green and not blinking. Use the table below for information on the Slammer bezel LEDs.
  • Page 130 Chapter 6 Complete the Installation Table 23 LEDs on the Slammer bezel (continued) Status Activity Fault Software Meaning module (at the PIM side only). ● The network interface module (NIM) or PIM is not detected. ● There is a initialization error.
  • Page 131: Figure 60 Slammer Bezel Leds

    Chapter 6 Complete the Installation Figure 60 Slammer bezel LEDs Legend 1 CU 0 2 CU 1 3 Fault LEDs 4 Activity LEDs 5 Status LEDs 4 Verify that the FAULT LEDs are off. If they are on at this stage, it is usually because the bezel is not fully seated. 5 For each Brick, make sure that the CU 0 and CU 1 STATUS LEDs are green.
  • Page 132: Figure 61 Brick Bezel Leds

    Chapter 6 Complete the Installation Figure 61 Brick bezel LEDs Legend 1 CU 0 STATUS light 2 CU 1 STATUS light 3 FAULT LED 4 Power light 5 Pillar logo 6 Verify that the FAULT LED for each Brick is off. A lit FAULT LED at this stage usually means the bezel is not fully seated.
  • Page 133: Verify The Back Status Leds

    Chapter 6 Complete the Installation Verify the Back Status LEDs At the back of the system: 1 Verify that the connectivity LEDs on each Pilot control unit (CU) are green. Blinking indicates activity, which may be normal during bootup. Sometimes the Ethernet LEDs are amber even when the Pilot boots up normally.
  • Page 134: Figure 63 Slammer Connectivity Leds

    Chapter 6 Complete the Installation Figure 63 Slammer connectivity LEDs Legend 1 Power supply LEDs 2 GbE network interface module (NIM) port LEDs 3 CU LEDs 4 Private interconnect module (PIM) Fibre Channel LEDs If you are using a Version 2 PIM, there must be a Caution cable from port FC3 to FS10.
  • Page 135: Figure 64 Brick Leds

    Chapter 6 Complete the Installation 3 On the Bricks, verify: ● The thumb-wheel on the Enclosure Services (ES) module is set to 0 for the following Brick types: Serial ATA (SATA), SATA Version 2, solid state drives (SSD), and Fibre Channel RAID (FC RAID). ●...
  • Page 136: Gb/S Fiber Channel (Fc) Hba Led Status

    Chapter 6 Complete the Installation Note: Use a wet finger to check if the Brick power supply fans are spinning. Some fan models have curved supports so that it look like the fan blades are not spinning. Related references 8 Gb/s Fiber Channel (FC) HBA LED Status •...
  • Page 137: 10 Gb/S Ethernet Hba Led Status

    Chapter 6 Complete the Installation 10 Gb/s Ethernet HBA LED Status Table 25 10 Gb/s Ethernet HBA LED status LED identifier and color Meaning Speed (left Solid green The HBA is operating at 10 Gb/s. LED) Solid yellow The HBA is operating at 1 Gb/s. No physical connection to the port or the port is not operational.
  • Page 138: Attach The Bezels

    Chapter 6 Complete the Installation Attach the Bezels You must attach all bezels or the system generates an error condition and lights the FLT LEDs amber. 1 Install all Pilot, Slammer, and Brick bezels as required. 2 For Bricks, at the front of the system, fully seat all drives by pressing each drive carrier into the Brick chassis.
  • Page 139: Figure 66 Press The Ejector Tabs To Secure The Bezel

    Chapter 6 Complete the Installation Figure 66 Press the ejector tabs to secure the bezel Legend 1 Press the ejector tabs to secure the bezel Attach the Bezels...
  • Page 140: About Hba Driver And Firmware Installation (San Only)

    About HBA Driver and Firmware Installation (SAN Only) You must install FC HBAs in the SAN hosts, including any software required by the HBAs, before you can access the LUNs on Pillar Axiom 600 servers. Complete the instructions from your HBA vendor to: ●...
  • Page 141: About Switch Zone For Hba Set Up (San Only)

    Chapter 6 Complete the Installation About Switch Zone for HBA Set Up (SAN Only) If appropriate, follow the instructions from your switch vendor to set up zones to: ● Permit host HBA ports to access the Slammer ports. ● Segregate network servers with different operating systems. ●...
  • Page 142: Attach The Rack Doors And Panels

    Chapter 6 Complete the Installation Attach the Rack Doors and Panels In this procedure, you reattach the front and back doors and both side panels to the rack. These steps help to ensure the security and proper cooling of Pillar Axiom 600 system components.
  • Page 143: Attach The Rack Side Panels

    Chapter 6 Complete the Installation Attach the Rack Side Panels 1 Hang the top of the panel on the top of the rack frame and latch the panel to close it. If the racks are bayed, you must install only the outer two panels. Important! Be sure not to pinch any cables that might have strayed from their proper moorings.
  • Page 144: Chapter 7 Initial Configuration

    Chapter 7 Initial Configuration HAPTER Initial Configuration Pre-Configuration Checklist To configure your system, you will need to have at hand certain information, such as IP addresses. You may want to print this list and check off each item after you complete it. Table 26 Global system parameters Done Information...
  • Page 145 Chapter 7 Initial Configuration Table 26 Global system parameters (continued) Done Information ❑ Get the management network subnet mask and the IP address for the gateway to be used. ❑ Decide whether you want the system to e-mail alerts to administrators. If so, get the IP address of your e-mail server.
  • Page 146: Start The Graphical User Interface

    Chapter 7 Initial Configuration Start the Graphical User Interface The Pillar Axiom Storage Services Manager is a graphical user interface (GUI) to manage the Pillar Axiom system. Access the GUI by connecting to the high- availability IP address of the Pilot, the default of which is 10.0.0.2. Do not connect the Pilot Management interfaces to the Caution customer network without checking to make sure that the...
  • Page 147: Figure 67 Pillar Axiom Storage Services Manager Log In Screen

    Chapter 7 Initial Configuration Figure 67 Pillar Axiom Storage Services Manager log in screen 5 For Axiom name, specify the Pillar Axiom system to which you want to connect. Valid values: ● IP address of the Pilot management controller. ● Name of the Pillar Axiom system as configured in your site naming services for the Pilot.
  • Page 148 Chapter 7 Initial Configuration The system status is displayed in the bottom left corner of the status bar of theGUI. A round green circle indicates that all hardware components in the Pillar Axiom system have successfully started and are operating normally. If warning the System Status icon is a yellow triangle (which indicates a critical condition), click Monitor >...
  • Page 149: Rename The Bricks

    Chapter 7 Initial Configuration Rename the Bricks The physical Brick names indicate the physical location of the Brick in the rack. The actual names or logical names, as seen in the Pillar Axiom Storage Services Manager GUI, might be different. Figure 68 Logical Brick names in the GUI The logical name of each Brick is determined during the installation and follows the scheme Brick001, Brick002, Brick003, and so on.
  • Page 150 Chapter 7 Initial Configuration 4 In the Bricks overview pane, highlight the name of the Brick that you want to modify. 5 (Optional) To identify physically the Brick you intend to rename, select Actions > Identify and, use the Identify dialog to flash the LEDs on the front and back of the selected Brick.
  • Page 151: Troubleshoot A Failed Cable Connection

    Cabling Reference . Contact the Pillar World Wide Customer Support Center for assistance after checking that all the cabling connections are correct as Pillar Axiom 600 SSF Cabling Reference . indicated in the 6 Contact the Pillar World Wide Customer Support Center for help in determining whether you have a bad cable or port and which one is bad: ●...
  • Page 152: About Pillar Axiom Path Manager Installation (San Only)

    ● Provides path failover. ● Streamlines system management. Important! Configure the LUNs on the Pillar Axiom 600 system before you install the APM system software on the SAN host. Pillar Axiom Path Manager Complete the procedures in the appropriate Installation Guide and Release Notes to install the APM driver and software on the SAN host.
  • Page 153: Reset The Primary System Administrator Password

    Chapter 7 Initial Configuration Reset the Primary System Administrator Password If you forget the Primary system administrator password, you can reset it. 1 Use a Type 1 Administrator account, if one exists, to reset the password. A support administrator cannot reset the Primary Administrator password. 2 If no Type 1 Administrator account is available, contact the Pillar World Wide Customer Support Center for the encrypted file (for resetting the password), which may be placed in a USB key.
  • Page 154: Appendix A Slammer Led Startup Progress Codes

    Tip: The FLT, ST, and ACT LED indicators are duplicated on the upper left of the PIM in the rear of the Pillar Axiom 600 system. If the Slammer halts during startup, the three LEDs on the back of the chassis (FLT, ACT, and ST) or the three LEDs on the bezel (Status, Activity, and Fault) help you identify where the Slammer halted in the startup sequence.
  • Page 155: About Slammer Led Codes

    Appendix A Slammer LED Startup Progress Codes About Slammer LED Codes The Slammer bezel has Fault, Status, and Activity LEDs that can display various colors and blink rates. These LEDs also appear on the private interface module at the back of the Slammer chassis, and are labeled FLT (Fault), ACT (Activity), and ST (Status).
  • Page 156: Slammer Led Startup And Halt Codes

    Appendix A Slammer LED Startup Progress Codes Slammer LED Startup and Halt Codes The following table describes the meaning of the Slammer startup and halt codes as indicated by the LEDs. The system may go through this sequence more than once if the network is having trouble responding.
  • Page 157: Table 28 Slammer Led Boot Block Error Codes

    Appendix A Slammer LED Startup Progress Codes Table 28 Slammer LED boot block error codes Code Software module Meaning Rapid Rapid EEL_BATTERY_MISSING_ERR Battery is not orange green present. Rapid Slow green EEL_BATTERY_LOW_ERR Battery orange voltage is low (below 5.5 V). Slow Rapid EEL_VRT_CLEAR_ERR...
  • Page 158 Appendix A Slammer LED Startup Progress Codes Table 28 Slammer LED boot block error codes Code Software module Meaning Rapid Rapid EEL_CLAMP_STATUS_UNKNOWN_ CPLD green green memory clamp is in an indeterminate state. Rapid Slow green EEL_CRC_FAILED A PROM green sector has an invalid CRC.
  • Page 159: Table 29 Slammer Led Ram Loader Codes

    Appendix A Slammer LED Startup Progress Codes Table 28 Slammer LED boot block error codes Code Software module Meaning output for details. Table 29 Slammer LED RAM loader codes Code Software module Meaning Rapid EEL_MAIN Entered "C" code main routine. Rapid Slow EEL_INIT_IDT...
  • Page 160 Appendix A Slammer LED Startup Progress Codes Table 29 Slammer LED RAM loader codes (continued) Code Software module Meaning Rapid Slow EEL_CONTINUE Exited the orange ramloader monitor (diagnostic environment only). Rapid Slow Green EEL_MPOST About to enter orange MPOST (diagnostic environment only).
  • Page 161: Table 30 Slammer Led States After Post Process Completion

    Appendix A Slammer LED Startup Progress Codes Table 29 Slammer LED RAM loader codes (continued) Code Software module Meaning Rapid Rapid Slow EEL_EEPROM_DATA_ERROR Unrecognized green orange DIMM size is installed. Rapid Rapid Slow green EEL_MEMTEST About to start green memory test. Rapid Slow EEL_MEMTEST_FAILED...
  • Page 162: Appendix B Safety Statements

    PPENDIX Safety Statements About Safety Statements For the Pillar Axiom 600 system, safety statements provide specific warning and cautionary notices about the electrical and weight properties that are associated with a Pillar Axiom 600 system and its hardware components. Important! Procedures listed in the body of this document assume that the...
  • Page 163: Warning Notices

    Appendix B Safety Statements Warning Notices This hazard symbol means warning. You are in a situation Warning that could cause bodily injury. Before you work on any equipment, be aware of the hazards that are involved with electrical circuitry and be familiar with standard practices for preventing accidents.
  • Page 164 Appendix B Safety Statements Table 31 Electrical warning in other languages (continued) ai circuiti elettrici ed essere al corrente delle pratiche standard per la prevenzione di incidenti. Advarsel Dette varselsymbolet betyr fare. Du befinner deg i en situasjon som kan fØre til personskade. FØr du utfØrer arbeid på utstyr, må...
  • Page 165 To reduce the risk of electric shock, disconnect all power supply cords to these components before you open their top covers. The Pillar Axiom 600 system operates at high voltages. To Warning protect against physical harm, power off the system whenever possible during installation.
  • Page 166: Lightning Activity Warning

    Appendix B Safety Statements Never block the inlet and outlet holes in the chassis Warning components. Sufficient air circulation is required for the components to operate properly and to avoid a fire hazard. Do not push objects of any kind into the ventilation holes. Such action could result in fire or electrical shock.
  • Page 167: Power Supply Warning

    Appendix B Safety Statements Table 32 Lightning warning in other languages (continued) Aviso Não trabalhe no sistema ou ligue e desligue cabos durante perÍ odos de mau tempo (trovoada). Advertencia No operar el sistema ni conectar o desconectar cables durante el transcurso de descargas eléctricas en la atmósfera. Varning Vid å...
  • Page 168 Appendix B Safety Statements Table 33 Power supply warning in other languages (continued) Attention Ne pas toucher le bloc d'alimentation quand le cordon d'alimentation est branché. Avec les systèmes munis d'un commutateur marche-arrêt, des tensions de ligne sont présentes dans l'alimentation quand le cordon est branché, même si le commutateur est ààl'arrêt.
  • Page 169: Main Power Disconnect Warning

    Appendix B Safety Statements Table 33 Power supply warning in other languages (continued) Varning Vidrör inte strömförsörjningsenheten nä r nä tsladden ä r ansluten. För system med strömbrytare finns det nä tspä nning i strömförsörjningsenheten ä ven nä r strömmen har slagits av men nä...
  • Page 170: Power Disconnect Warning

    Appendix B Safety Statements Table 35 Installation warning in other languages (continued) Varoitus Lue asennusohjeet ennen jä rjestelmä n yhdistä mistä virtalä hteeseen. Attention Avant de brancher le système sur la source d'alimentation, consulter les directives d'installation. Warnung Lesen Sie die Installationsanweisungen, bevor Sie das System an die Stromquelle anschließ...
  • Page 171: Restricted Access Area Warning

    Appendix B Safety Statements Restricted Access Area Warning This unit is intended for installation in restricted access Warning areas. A restricted access area is where access can only be gained by service personnel through the use of a special tool, lock and key, or other means of security, and is controlled by the authority responsible for the location.
  • Page 172: Product Disposal Warning

    Appendix B Safety Statements Table 37 Restricted access warning in other languages (continued) Avvertenza Questa unitàdeve essere installata in un'area ad accesso limitato. Un'area ad accesso limitato è un'area accessibile solo a personale di assistenza tramite un'attrezzo speciale, lucchetto, o altri dispositivi di sicurezza, ed è controllata dall'autoritàresponsabile della zona.
  • Page 173: Product Disposal Warning In Other Languages

    Appendix B Safety Statements Product Disposal Warning in Other Languages Table 38 Product disposal warning in other languages Waarschuwing Dit produkt dient volgens alle landelijke wetten en voorschriften te worden afgedankt. Varoitus Tä mä n tuotteen lopullisesta hä vittä misestä tulee huolehtia kaikkia valtakunnallisia lakeja ja sä...
  • Page 174: Jewelry Removal Warning In Other Languages

    Appendix B Safety Statements Jewelry Removal Warning in Other Languages Table 39 Jewelry removal warning in other languages Waarschuwing Alvorens aan apparatuur te werken die met elektrische leidingen is verbonden, sieraden (inclusief ringen, kettingen en horloges) verwijderen. Metalen voorwerpen worden warm wanneer ze met stroom en aarde zijn verbonden, en kunnen ernstige brandwonden veroorzaken of het metalen voorwerp aan de aansluitklemmen lassen.
  • Page 175: Qualified Personnel Warning

    Appendix B Safety Statements Table 39 Jewelry removal warning in other languages (continued) Aviso Antes de trabalhar em equipamento que esteja ligado a linhas de corrente, retire todas as jó ias que estiver a usar (incluindo anéis, fios e reló gios). Os objectos metá licos aquecerão em contacto com a corrente e em contacto com a ligação àterra, podendo causar queimaduras graves ou ficarem soldados aos terminais.
  • Page 176: Warning Statement For Finland

    Appendix B Safety Statements Table 40 Qualified personnel warning in other languages (continued) Advarsel Kun kvalifisert personell med riktig opplæring bØ r montere eller bytte ut dette utstyret. Aviso Este equipamento deverá ser instalado ou substituÍ do apenas por pessoal devidamente treinado e qualificado. Atenció...
  • Page 177: Power Cabling Warning In Other Languages

    Appendix B Safety Statements Power Cabling Warning in Other Languages Table 43 Power cabling warning in other languages Waarschuwing Zet alle stroomkabels vast wanneer dit toestel wordt geÏnstalleerd om te voorkomen dat de verbindingen van de veldbedrading worden verstoord. Varoitus Kiinnitä...
  • Page 178: Supply Circuit Warning

    Appendix B Safety Statements Supply Circuit Warning Do not overload the circuit when you connect components Warning to the power supply. Supply Circuit Warning in Other Languages Table 44 Supply circuit warning in other languages Waarschuwing Let erop dat de toestellen op voedingscircuits worden aangesloten zonder het vermogen van de bedrading te overschrijden.
  • Page 179: Voltage Mismatch Warning

    Appendix B Safety Statements Voltage Mismatch Warning A voltage mismatch can cause equipment damage and may Warning pose a fire hazard. If the voltage indicated on the label do not connect the differs from the power outlet voltage, chassis to that receptacle . Voltage Mismatch Warning in Other Languages Table 45 Voltage mismatch warning in other languages Waarschuwing...
  • Page 180: Selv Circuit Warning

    Appendix B Safety Statements Table 45 Voltage mismatch warning in other languages (continued) forskjellig fra spenningen i stikkontakten, må du ikke koble kabinettet til den stikkontakten. Aviso Uma voltagem incorrecta poderá causar danos no equipamento e constituir um risco de incêndio. Se a voltagem indicada na etiqueta for diferente da voltagem de saÍ...
  • Page 181 Appendix B Safety Statements Table 46 SELV circuit warning in other languages (continued) Varoitus Jotta vä ltyt sä hköiskulta, ä lä kytke pienjä nnitteisiä SELV- suojapiirejä puhelinverkkojä nnitettä (TNV) kä yttä viin virtapiireihin. LAN-portit sisä ltä vä t SELV-piirejä ja WAN- portit puhelinverkkojä...
  • Page 182: Incorrect Connection Warning

    Appendix B Safety Statements Table 46 SELV circuit warning in other languages (continued) SELV) con circuitos de voltaje de red telefó nica (telephone network voltage = TNV). Los puertos de redes de á rea local (local area network = LAN) contienen circuitos SELV, y los puertos de redes de á...
  • Page 183 Appendix B Safety Statements Table 47 Connection warning in other languages (continued) Avvertenza Un collegamento errato di questo apparecchio, o dell'apparecchiatura a esso collegato, a una presa di uso generale pu\x98 causare una situazione pericolosa. Advarsel Feil kobling av dette utstyret eller tilhØ rende utstyr til et vanlig uttak kan fØ...
  • Page 184: Caution Notices

    Caution that of the room. With regard to the maximum rated ambient for Pillar Axiom 600 components, do not reduce the amount of airflow that is required for safe operation. Never block the ventilation holes in a chassis. Sufficient air...
  • Page 185 Appendix B Safety Statements Qualified personnel are advised to exercise great care at all Caution times when they work on a Pillar Axiom 600 system. Remember to: ● Remove rings, watches, or other jewelry and neckties before you begin any procedure.
  • Page 186: Appendix C Pillar Axiom Hardware Specifications

    Pillar Axiom Hardware Specifications About Hardware Specifications Hardware specifications (sometimes called data sheets): ● Describe the system's operating environment. ● List the agency approvals. ● List physical attributes of the Pillar Axiom 600 system and its hardware components. About Hardware Specifications...
  • Page 187: About Pillar Axiom 600 Hardware Specifications

    Pillar Axiom 600 PDU Hardware Specification • System Power Requirements Pillar Axiom 600 systems require at least two feeds, in which both have one of the power input characteristics shown below. The voltage and frequency show minimum and maximum values.
  • Page 188: System Environmentals

    +41 to 104°F (+5 to 40°C) Up to 10,000 feet elevation: +41 to 95°F (+5 to 35°C) Non- -22 to 158 °F 5–95% 104°F 54°F/hr operational (-30 to 70 °C) 10%/hr (40°C) (30°C/hr) gradient About Pillar Axiom 600 Hardware Specifications...
  • Page 189: Table 51 System Acoustics Specification

    Note: For Bricks that have five-platter drives, the maximum ambient operational temperature from 7000 feet to 10,000 feet is 95°F (35°C). System Acoustics Acoustics for a Pillar Axiom 600 system that comprises the following components were tested to ISO 7779 by standard specifications: ● One Pilot ●...
  • Page 190: System Regulatory Agency Compliance

    Appendix C Pillar Axiom Hardware Specifications System Regulatory Agency Compliance Agency approvals are based on a Pillar Axiom 600 system that consists of: ● One Pilot ● Two Slammers ● Twelve Bricks Related references Regulatory Compliances • FCC Warning Statement •...
  • Page 191 PCB, PCA reliability. Pillar will continue to work with industry consortia to define common qualification criteria. Pillar will apply Pb-free solder technologies to product designs as required by legislation. ISO 9001:2000 Registered manufacturing process. About Pillar Axiom 600 Hardware Specifications...
  • Page 192 Appendix C Pillar Axiom Hardware Specifications Table 53 Safety, quality, and environmental standards (continued) Logo Standard Compliance packaging label: SPS1. Compliance packaging label: SPR1. Compliance packaging label: SPA1. KCC-SPS1. KCC-SPR1. KCC-SPA1. BSMI D-Mark. About Pillar Axiom 600 Hardware Specifications...
  • Page 193: Table 54 Electromagnetic (Em) Emissions And Immunity

    This equipment generates, uses, and can radiate radio-frequency energy and, if not installed and used in accordance with the instruction manual, may cause harmful interference to radio communications. Operation of this equipment in a About Pillar Axiom 600 Hardware Specifications...
  • Page 194: European Union Compliance Statement

    We have signed a Declaration of Conformity with the requirements of the Directive. The following standards were applied: 1 Emissions: EN55022 (Class A radiated and conducted, 110V, 230V) 2 EMC: EN55024 (immunity): ● EN 61000-3-2 About Pillar Axiom 600 Hardware Specifications...
  • Page 195: System Packaging And Transportation

    GR-63-CORE, Packaged Equipment Shock (4.3.1), Office Vibration (4.4.3) and Transportation Vibration (4.4.4). System Warranty Hardware components in a Pillar Axiom 600 system are covered by a three-year warranty. Note: The hardware and software warranty for all Pillar Axiom 600 products applies to the system, not to individual components like Slammers and Bricks within the system.
  • Page 196: About Pilot Hardware Specifications

    Appendix C Pillar Axiom Hardware Specifications About Pilot Hardware Specifications A Pilot is an active management and provisioning front end as well as the administrator interface to a Pillar Axiom 600 system. Pilot Dimensions and Weight Table 55 Pilot dimensions and weight (both control units)
  • Page 197: Pilot Regulatory Agency Compliance

    Appendix C Pillar Axiom Hardware Specifications Table 56 Pilot power characteristics (for each control unit) (continued) Power characteristic Value Maximum heat dissipation 750BTU/hr AC plug type 2 IEC 320 connection Pilot Regulatory Agency Compliance This equipment has been tested and found to comply with the limits for a class B digital device, pursuant to part 15 of the FCC rules.
  • Page 198: Pilot Packaging And Transportation

    Appendix C Pillar Axiom Hardware Specifications Table 57 Pilot safety and quality standards Logo Standard FCC (United States). This device complies with FCC Rules Part 15 for a class B digital device. Conformite Europeenne /DoC Pilot Packaging and Transportation Pilot packaging meets the following requirements: ●...
  • Page 199: About Slammer Hardware Specification

    Appendix C Pillar Axiom Hardware Specifications About Slammer Hardware Specification Slammers are fully redundant controllers within a Pillar Axiom 600 system. A Slammer can be ordered as either a SAN or a NAS front end. Slammer Dimensions and Weight Table 58 Slammer dimensions and weight...
  • Page 200: Slammer Regulatory Agency Compliance

    Appendix C Pillar Axiom Hardware Specifications Table 59 Slammer power characteristics (continued) Power characteristic Value AC plug type Four IEC 320 C13 connection Slammer Regulatory Agency Compliance Slammers comply with the following regulatory agency requirements. Table 60 Slammer safety and quality standards Logo Standard FCC (United States).
  • Page 201: Cable Length Limits For San Fibre Channel Connections

    Appendix C Pillar Axiom Hardware Specifications ● For packages over 150 lb—Network Equipment Building System (NEBS) core standards. GR-63-CORE, Packaged Equipment Shock (4.3.1), Office Vibration (4.4.3) and Transportation Vibration (4.4.4). Cable Length Limits for SAN Fibre Channel Connections SAN Fibre Channel (FC) ports on Slammer network interface modules (NIMs) connect to SAN switches using Fiber Channel cables of specified lengths.
  • Page 202: Table 62 Cable Lengths Limitations (10 Gb/S Optical Short Range)

    Appendix C Pillar Axiom Hardware Specifications Table 62 Cable lengths limitations (10 Gb/s optical short range) Multimode Fiber Minimal modal OM type Maximum cable (MMF) optical bandwidth with length cable type core short range diameter 850nm laser (micrometers) (MHz*km) 62.5/125 85.28 feet (26 meters) 62.5/125...
  • Page 203: About Brick Hardware Specification

    Appendix C Pillar Axiom Hardware Specifications About Brick Hardware Specification A Brick is a high-performance disk subsystem with an optimized, proprietary RAID controller. Brick Dimensions and Weight Table 64 Brick dimensions and weight Attribute Value Height 3.5 inches (8.89 centimeters); Width 17.72 inches (45 centimeters) Depth...
  • Page 204: Brick Regulatory Agency Compliance

    1127 BTU/hr AC plug type Two IEC 320 connections Brick Regulatory Agency Compliance Pillar Axiom 600 Bricks comply with the following regulatory agency requirements. Table 66 Brick safety and quality standards Logo Standard FCC (United States). This device complies with FCC Rules Part 15.
  • Page 205: Brick Packaging And Transportation

    Appendix C Pillar Axiom Hardware Specifications Table 66 Brick safety and quality standards (continued) Logo Standard ISO 9001:2000 Registered manufacturing process Brick Packaging and Transportation Packaging meets the following requirements: ● For packages under 150 lb—International Safe Transit Association (ISTA 2A) Procedures 1 and 2.
  • Page 206: Pillar Axiom 600 Pdu Hardware Specification

    Appendix C Pillar Axiom Hardware Specifications Pillar Axiom 600 PDU Hardware Specification If you install non-Pillar PDUs, they must meet the Pillar Axiom 600 PDU specification, as outlined below. When you intend to use non-Pillar PDUs, check first with your Pillar Account Representative to ensure you do not jeopardize your system warranty by installing the non-Pillar PDUs.
  • Page 207 25 db @ 1MHz. Differential mode: Differential mode: Differential mode: 30 db @ 1MHz. 30 db @ 1MHz. 22 db @ 1MHz. MHz/db: .15/6, .50 MHz/db: .15/6, .50 MHz/db: .15/6, .50 Surge 270VAC 320VAC 275VAC suppression Pillar Axiom 600 PDU Hardware Specification...
  • Page 208: Pillar Rack Hardware Specification

    Appendix C Pillar Axiom Hardware Specifications Pillar Rack Hardware Specification A Pillar Axiom 600 42U rack can contain any combination of: ● One Pilot. ● One to four Slammers, which can be a mix of network attached storage (NAS) and storage area network (SAN) Slammers.
  • Page 209 Appendix C Pillar Axiom Hardware Specifications Table 68 Rack specifications for a Pillar Axiom 600 system (continued) Criteria Pillar rack Non-Pillar rack (minimum requirements) Depth (outside) 39.5 inches (100.3 centimeters) 43 inches (109.2 centimeters) maximum Front door ● Vented ● Vented ●...
  • Page 210: Figure 69 Maximum Tilt Angles For Stationary Pillar 42U Racks

    Appendix C Pillar Axiom Hardware Specifications Table 68 Rack specifications for a Pillar Axiom 600 system (continued) Criteria Pillar rack Non-Pillar rack (minimum requirements) ● 64 outlets (for single phase PDU) Note: 48 outlets (for three phase PDUs) with two maximum PDUs (115/208V 30A for US and 230/400V 16A for EU).
  • Page 211: Appendix D Expansion Of A Pillar Axiom 600 System Configuration

    Brick storage enclosures and Slammer storage controllers to an existing Pillar Axiom 600 system. A Pillar Axiom 600 can have a maximum number of four Slammers and 64 Bricks attached to the system. The Pillar Axiom 600 system allows you to start your storage system with a small configuration and later, scale up to larger configurations without a disruption to the data access.
  • Page 212: Complete The Slammer Pre-Installation Checklist

    Add a New Brick Storage Enclosure • Complete the Slammer Pre-Installation Checklist Prior to adding new Slammers to a pre-existing Pillar Axiom 600 system, complete the tasks outlined in the pre-installation checklist. ● Inventory the Slammer and installation components to make sure you have the correct cables and mounting hardware.
  • Page 213: About Additional Brick Storage Enclosures

    About Additional Brick Storage Enclosures You can add Bricks to expand a Pillar Axiom 600 system. Addition of Bricks to the end of an existing Brick string in a Pillar Axiom 600 system is non-disruptive. Note: Addition of Bricks may be disruptive if additional power distribution units (PDUs) are required to fulfil power requirements.
  • Page 214: Add A New Brick Storage Enclosure

    Pillar Axiom 600 SSF Cabling 2 Cable the new Bricks as described in the Reference . You do not need to power down the Pillar Axiom 600 system to cable additional Bricks. Note: When adding additional Bricks, there may be changes in the existing Pillar Axiom 600 SSF cabling of the Pillar Axiom 600 system.
  • Page 215 They are seated correctly if they do not go in any further and none extend out more than the others. 6 Make sure the Pillar Axiom 600 system is powered on and all the new cables are in place. Important! Ensure that the Pillar Axiom 600 system is in Normal status and...
  • Page 216 Administrator account to accept the new Brick. Result: When you add a Brick storage enclosure to an existing Pillar Axiom 600 system, the system begins the process to bring the Brick online. While the system is bringing the Brick online, you may see a series of error and warning messages similar to these: ●...
  • Page 217: Verify A Newly Added Brick

    While adding new Bricks, verify the status of each Brick as the Brick is powered on to ensure that it has been added to the Pillar Axiom 600 system configuration. Do not wait to conduct the status checks after a few Bricks have been added because doing the status check in a batch might increase the possibility of bringing other resources offline.
  • Page 218: About Additional Slammer Storage Controllers

    Note: Disconnect a Brick only if there is a private interconnect (PI) issue. Related tasks Add a New Brick Storage Enclosure • About Additional Slammer Storage Controllers You can add Slammers to expand a Pillar Axiom 600 system. About Expanding a Pillar Axiom 600 Configuration...
  • Page 219: Add A New Slammer Storage Controller

    1 PIMs and Slammers with version 2 PIMs. Add a New Slammer Storage Controller 1 Using the GUI or command line interface (CLI), place the Pillar Axiom 600 system in Shutdown Status and verify that the system has successfully shut down.
  • Page 220: Storage System Fabric (Ssf) Cabling Reference

    • Storage System Fabric (SSF) Cabling Reference When adding an additional Slammer to a Pillar Axiom 600 system, you need to move some Fibre Channel (FC) cables to different ports on the private interconnect module (PIM). The cable swapping differs depending on the PIM.
  • Page 221: Table 69 Slammer Cross Connection Configuration Version 1 Pims

    Appendix D Expansion of a Pillar Axiom 600 System Configuration Table 69 Slammer cross connection configuration version 1 PIMs Legend 1 First Slammer. 2 Second Slammer. 3 Third Slammer. 4 Fourth Slammer. 5 Move the red FC cables when expanding the system to the next larger configuration.
  • Page 222: Table 70 Slammer Cross Connection Configuration Version 2 Pims

    Appendix D Expansion of a Pillar Axiom 600 System Configuration Table 70 Slammer cross connection configuration version 2 PIMs Legend 1 First Slammer. 2 Second Slammer. 3 Third Slammer. 4 Fourth Slammer. 5 Move the red FC cables when expanding the system to the next larger configuration.
  • Page 223: Table 71 Swapping Head-Of-String Brick Cables

    Appendix D Expansion of a Pillar Axiom 600 System Configuration Table 71 Swapping head-of-string Brick cables Legend 1 First Slammer. 2 Second Slammer. 3 Third Slammer. 4 Fourth Slammer. 5 Move the red FC cables when expanding the system to the next larger configuration.
  • Page 224: Index

    Index 10 Gb/s Ethernet HBA bracket, rack connector LED status Brick hardware components 2U rack rails expanding the system Bricks hardware specifications Pilots how to 4U rack rails add a new Brick 8 Gb/s Ethernet HBA install LED status install rack rails power on replace accept...
  • Page 225 (ESD) components environment, data center Pillar Axiom 600 Pillar Axiom system requirements components, Pillar Axiom 600 system equipment, required technical specifications ES modules, Brick components, Pillar Axiom system location placement in rack...
  • Page 226 definition cable PMI cable SSF handle fiber optic cables humidity specifications gigabit Ethernet switches graphical user interface (GUI) how to login identities ground straps how to door set for Bricks precautionary use of installation procedures cable multiple racks connect PDUs to power create a rack bay halt, Slammer attach baying plates...
  • Page 227 Pillar Axiom 600 professional services configuration limits progress codes, Slammer startup Pillar Axiom 600 system hardware specifications Pillar Axiom Path Manager (APM) rack bays about installation attach baying plates Pillar Axiom storage system interconnection bracket...
  • Page 228 install for Pilots power on install for Slammers test SSF connections racks LED codes 155 , 156 doors and panels halt EIA-310-D compliance startup how to LED status level 10 Gb/s Ethernet HBA stabilize using anti-tip brackets 8 Gb/s Ethernet HBA stabilize using stabilizer plates mixing PIM versions test SSF configuration...
  • Page 229 accept Brick 214 , 217 system, Pillar Axiom how to test the configuration warranty technical documents accessing technical support temperature specifications tie-down system, sub-floor tools, required training programs turn on Pillar Axiom systems TUV/GS compliance typographical conventions versions, hardware component PIMs vibration specifications, system warnings...

Table of Contents