Note: In a system that is configured for the maximum number of Bricks, connect
the additional racks to the first rack before you install and cable the hardware
components.
Related concepts

About Component Placement for Four Slammers and 64 Bricks

Sample Power Cabling for One Slammer and Three Bricks
Related references
Cabling Practices for the Pillar Axiom 600 System
Related tasks
Rename the Bricks
About Component Placement for Four Slammers and 64 Bricks
Pillar Axiom 600 systems with four Slammers support up to 64 Serial ATA
(SATA) Bricks, or a combination of up to 32 FC Bricks and 32 SATA Bricks in a
mixed system.
Note: This topic applies only to Pillar Axiom 600 systems.
Install the components in the rack as shown in the following figure, which
illustrates how the Pillar Axiom 600 system components are mapped into a fully
loaded 42U racks for the maximum configuration of:
● 1 Pilot
● 4 Slammers
● 64 Bricks