6D3–20 STARTING AND CHARGING SYSTEM (6VD1 3.2L)

Installation

1. Install generator assembly to the position.
2. Install generator assembly and tighten the fixing bolts
to the specified torque.
Torque:
M10 bolt: 41 N·m (30 Ib ft)
M8 bolt: 21 N·m (15 Ib ft)
3. Connect wiring harness connector and direct terminal
"B".

Disassembled View

Legend
(1) Pulley Nut
(2) Pulley
(3) Front Cover Assembly
(4) Rotor Assembly
(5) Stator Assembly
(6) Through Bolt
4. Move drive belt tensioner to loose side using wrench,
then install drive belt to normal position.
5. Reconnect battery ground cable.
(7) Nut
(8) Terminal Insulator
(9) Rear Cover Assembly
(10) Rectifier
(11) Brush Holder Assembly
(12) Regulator Assembly
066RW022