The pre-start-up checklist must be completed by installing contractor. For Carrier factory start-up, the pre-start-up checklist must
be submitted to the Carrier start-up team prior to arranging start-up. Please refer to the unit submittal or air balance report for air-
flow information.
PROJECT INFORMATION
Project Name _______________________________________
Address ___________________________________________
City ______________________________________________
State/Providence _________________ Zip Code __________
UNIT INFORMATION
Model Number _____________________________________
Software Version ___________________________________
INSTRUCTIONS
Check the box to verify the activity has been completed. If the activity does not apply, write N/A in the box.
Installation
All packing materials have been removed from the unit.
The compressor or supply fan shipping hold down brackets (if equipped) have been removed.
The unit is free of damage. If damage exists, contact your local Carrier representative.
The unit has been installed in accordance with the service clearances in the installation instructions.
The supply and return ductwork have been installed per the unit installation instructions.
The unit is within level tolerances to promote proper condensate drainage.
The evaporator filters are installed and are clean.
A properly sized condensate drain trap has been installed and is free from obstructions.
All required field-installed components or accessories (hoods, sensors, ERV, etc.) have been installed.
Electrical
The unit power feed is installed, and the phasing is correct (L1, L2, L3).
The unit voltage and frequency have been verified to match the incoming power feed.
The power feed wire size meets the MCA requirements on the unit nameplate.
An overcurrent production device (fuse or breaker) has been installed upstream of the unit and is sized less than or equal to the
MOCP requirements indicated on the unit nameplate.
A means of disconnecting and locking out electrical service at the unit has been provided.
All electrical connections and terminals are tight; all terminals are free from corrosion.
For high SCCR (ETO), field-provided J-type fuses have been installed before the unit terminal block.
Supply Fan
The supply fan(s) is free from obstruction and rotates properly; set screws are tight.
The supply fan belt has been installed and is at the proper tension.
The supply fan pulley and motor pulley are in alignment; shipping tape removed from pulleys.
All supply fan bearings have been inspected and verified to contain grease.
For VAV units, pneumatic tubing with a duct pressure pickup has been installed.
The pressure pick-up pneumatic tubing is free from obstruction or kinks.
Cooling
The air-cooled condenser coil(s) is clean and free from obstructions and defects.
The condenser fan motors rotate freely and are positioned correctly in the condenser housing.
The evaporator coils are clean and free from obstructions and defects.
The crankcase heaters are verified to be operational and will operate 24 hours prior to cooling start-up.
For units requiring mechanical cooling below 32°F ambient, wind baffles have been installed.
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53480461-01
PRE-START-UP CHECKLIST FOR SUMMER (COOLING)
Printed in U.S.A.
Installer
________________________________________
Contact Name ______________________________________
Contact Phone ______________________________________
Contact Email ______________________________________
Serial Number ______________________________________
Unit Tag/Name _____________________________________
Form No. 48-50P-13T Rev.A
Pg CL-1