Date
1-1-89.
Page-____
13_-_3a _ _
MC-9 MAINTENANCE MANUAL
5. Remove counters haft support tool from rear case bore and
install countershaft rear bearing with the larger 1.0. lead chamfer
toward front of transmission (figure 13-146).
Figure 13-146. Rear Bearing Installation.
NOTE: If damage to original bearing resulted
from punch and maul removal, replace with
new rear bearing.
6. Shift the mainshaft sliding clutches into all gear positions with
a screwdriver. A sliding cl_utch that cannot be shifted into gear indi-
cates that the drive gear set 1s out of time_ The right countershaft
bearings would then need to be removed and the countershaft
retimed with the main shaft. The transmission is properly timed if the
sliding clutches can be shifted into all mamshaft gears (figure
13-147).
Figure 13-147. Checking Sliding Clutches.
NOTE: Do not shift the transmission into
two gears at the same time. This will prevent •
the mainshaft and countershaft assemblies
from rotating.
7. If properly timed, install both countershaft rear bearing cov-
ers with new gaskets and secure to case with capscrews (figure
13-148).
Figure 13•148. Cover Installation.
REASSEMBLY AND INSTALLATION OF
LEFT REVERSE IDLER GEAR ASSEMBLY
NOTE: Since the left and right reverse idler
gear assemblies are identical, reassembly
and installation of the left reverse idler gear
assembly should be performed in the same
manner as described for right reverse idler
gear in previous pages of this section.
COMPLETING INSTALLATION OF MAINSHAFT
1. Remove the temporarily installed output shaft assembly from
case bore and coupling gear from rear of mainshaft (figure
13-149).
-
Figure 13-149. Removing Output Shaft and Coupling Gear.