SHIFT BAR HOUSING REMOVAL AND DISASSEMBLY
1. Turn out the attaching capscrews (figure 13-7). Jar to
break the gasket seal and lift the shift bar housing from the
transmission (figure 13-8).
NOTE: Lay all parts on a clean bench in the·
order in which' they are removed to facili-
tate reassembly. Keep bars not being re-
moved in the neutral position or interlock
parts will lock bars.
Figure 13-7. Removing Capscrews.
Figure 13-8. Removing Shift Bar Housing.
2. Turn out the two capscrews and remove the tension
spring cover from top of housing.
3. Remove the three tension springs from bores. in housing
(figure 13-9) and the gasket for tension spring cover.
Figure 13-9. Tension Spring Removal.
4. Tilt housing and remove the tension balls installed under
springs (figure 13-10).
Figure 13-10. Removing Tension Balls.
5. Place the housing in a vise with the left side up: the long
bar will be at the bottom ~figure 13-11 ).
Figure 13-11. Positioning Housing In Vise.