Putting the Example into Operation

Commissioning
1. Switch on the power supply of the ET 200iSP.
2. Observe the status LED at the S7-400 and at the ET 200iSP:
LEDs of the CPU:
– RUN: on (means: LED lights up)
– All other LEDs: off (means: LED does not light up)
For PROFINET configuration - LEDs on the interface module IM 152-1PN of the ET 200iSP:
– ER: Off
– MT: Off
– ACT: Off
– RN: on
– PS1: On, PS2: Off
– LK1 and/or LK2: on (when a network connection is set up from one device to another;
For PROFIBUS configuration - LEDs on the interface module IM 152-1DP of the ET 200iSP:
– SF: Off
– BF: Off
– ACT: Off
– ON: on
– PS1: On, PS2: Off
3.13

Evaluating the diagnostics

Evaluating the diagnostics
If an error occurs, OB82 is started. Evaluate the startup information in OB82.
Tip: Call the SFC13 within the OB82 and evaluate the diagnostics frame from section
"Commissioning and Diagnostics (Page 155)".
ET 200iSP
Operating Instructions, 11/2022, A5E00247483-AK
otherwise off)
Commissioning guideline
3.13 Evaluating the diagnostics
55