Be aware that the correct height to the bottom side of the foot print of
the vertical frame relative to the ground level of the top of road (=
charging position of the bus) must be calculated by ABB. Contact ABB
Sales department (see Contact information on Page 14 for contact
details).
8.
Tighten the nuts with a tightening torque of 590.05 ft-lb when no copper fat is used, and
with a tightening torque of 390.91 ft-lb when copper fat is used.
9.
Screw the second M24 nuts on the bolts (16x)
10. Tighten the upper nuts.
11. Remove the hoisting equipment from the Charge Pole.
5.14.

Install mast boom onto column

Preconditions:
Tools: mobile elevated work platform, torx screwdriver (size 2163TX-T30), spanner
(size 17 and 24), torque wrench (size 24).
1.
Connect the hoisting equipment to the lifting points on the mast boom (B) position of the
transport holder (A).
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022
HVC‐PD E‐Bus Charger Installation Guide 