9.
The conduits must be installed with a curve inside the foundation in order to prevent water
from entering the conduits, and seal the space between the conduits and all open holes.
10. Route the AC power cable through one of the eight holes (B). Make sure that a cable
length of 39.37 Inch is available above the surface of the foundation for internal routing in
the cabinet.
This extra cable length is required to connect the AC power cable with
the connectors in the Power Cabinet without problems.
11. Place both cover plates on the appropriate place on the foundation.
12. Secure the top cover plate with M16 bolts (4x) and the front cover plate with M12 bolts
(4x).
These cover plates are required to prevent people from falling into the
foundation.
13. Fill the open space in the ground around the foundation and the channels for the
conduits with filling material (e.g. sand). Filling material is packed 2 – 3 times with a
packing machine until the desired ground level is obtained. Avoid having filling material
inside the foundation.
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022
HVC‐PD E‐Bus Charger Installation Guide 
NOTICE
WARNING
Page 41 of 146

Advertisement

Table of Contents
loading

Table of Contents