Installation
5.4.1
Remove the EVSE from the base
Generally the base replacement is done during the installation procedure, when the
EVSE is still on the shipping pallet.
Preliminary requirements
Procedure
1. Open all doors of the EVSE. Refer to
section 8.1.
2. Loosen the fasteners of the standard
base at the front door, the right door
and the left door. Remove the bolts.
3. Close the doors of the EVSE. Refer to
section 8.2.
4. Lift the EVSE from the base and the
pallet. Refer to section 4.3.1.
5.4.2
Install a base with side entrance
This procedure is relevant if it is not possible to pull the AC power cables through
the concrete foundation. In that situation you can lay the power cables on the floor,
guide them through a conduit and let them enter from the side of the EVSE.
Preliminary requirements
Procedure
1. Mark the position of the holes on the
ground. For the specifications, refer to
section 10.12.8.
2. Drill the fixing points (A).
3. Align the frame (B) with the threaded
holes.
4. Install the fasteners (C).
5. Tighten the fasteners to the correct
torque. For the specification, refer to
section 10.7.
6. Cut the wires to the correct lenght.
46
•
Installation engineer or
maintenance engineer
•
Drill with screw tap
•
Torque wrench
•
Wrenches
•
Base with side entrance.
If you have not included
this base in the initial order,
contact the manufacturer.
Refer to section 1.12.
9AKK108466A3703-EN | 001
A
C
B
A