Connect The Ac Utility Power Cable - ABB HVC-PD Installation Manual

Hide thumbs Also See for HVC-PD:
Table of Contents

Advertisement

Preferred cable route
1.
Route the AC utility cable to the terminal block (A). Refer to the figure for the preferred
cable route inside the cabinet (only within the HVC 150).
2.
Route the Interlock cable(s) to the terminal block (B). Refer to the figure for the preferred
cable route inside the cabinet.
3.
Route the CAN cable to the terminal block (B). Refer to the figure for the preferred cable
route inside the cabinet.

5.8.2. Connect the AC utility power cable

The AC utility power cable for the ACS Control Module is only connected
within the HVC 150 Power Cabinet, see for more details section Cabling
on Page 49.
A
Terminal block
B
AC utility power cable
1.
Move the cable towards the terminal block (A).
2.
Strip 0.43 Inch of the insulation from the ends of the wires.
3.
Crimp a ferrule onto the end of the wire.
4.
Loosen the connector screws.
5.
Insert the wires into the connectors, see table below:
Functional description
PE
L1
L2
L3
6.
Tighten the connector screws with a tightening torque of 1.0 ft-lb.
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022
NOTICE
Connector
Wire color
X341-1
Green/yellow
X341-2
Brown
X341-3
Orange
X341-4
Yellow
HVC‐PD E‐Bus Charger Installation Guide 
Page 76 of 146