5. Placement and Connection
5.1. About placement and connection
When the construction phase is finished, the HVC-PD E-Bus Charger can be placed and
connected.
The planning steps for the placement and connection phase are shown in the figure below.
Usually the procedure can be done within one day.
C1
Route the cables on Page 55.
C2
Unpack on Page 55.
C3
Move Power Cabinet to position on Page 57 and Install Power Cabinet onto the
foundation on Page 60.
C4
Connect the AC power cable on Page 66, Connect the DC power cables on Page 73,
and Connect the communication fiber cables on Page 85.
C5
Unpack the Charge Pole on Page 87.
C6
Move the Charge pole to position on Page 88, Install Charge Pole onto the foundation
on Page 90 and Pantograph adjustment on Page 97.
C7
Installation of the cables inside Charge Post on Page 103.
C8
Install cover plates on Page 118 and Grouting of the pole construction on Page 120.