ABB HVC-PD Installation Manual page 89

Hide thumbs Also See for HVC-PD:
Table of Contents

Advertisement

1.
Connect the hoisting equipment to the lifting points on the Charge Pole.
2.
Lift the Charge Pole by using slings and place the Charge Pole beside the trailer. In order
not to damage the Charge Pole, use a wooden beam (A) on which the end of the pole can
rest.
3.
Loosening the nut/bolt (B) (2x) (but do not remove those) on both side of the mast boom,
so that the mast boom can freely rotated.
4.
Remove the hoisting equipment only from transport holder (C).
5.
Lift the Charge Pole up by using slings which are only connected to the lifting points (D).
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022
HVC‐PD E‐Bus Charger Installation Guide 
Page 89 of 146