5.11.2.

Remove packaging

1.
Remove the packing foil from the Charge Pole (if present).
2.
Open the top side of the wooden box with the plate work.
3.
Keep the bag with bolts and nuts to assemble the pole in a safe place.
5.12.

Move the Charge pole to position

Preconditions:
The location is prepared for placing the Charge Pole.
The location is closed to bystanders and all preparatory safety measures required
during the lifting operations have been carried out.
The Charge Pole is made unsecured on the trailer and the cover sail (if present) are
removed.
The protective cups to cover the bolts of the foundation are removed and the bolts are
free from dust. If necessary clean the bolts with a vacuum cleaner or brush.
The work must be carried out by at least two persons. One person to operate the
hoisting equipment, the other to guide the Charge Pole.
Tools: spanner (size 36).
Make sure that the main switch of the power supply group for the product
is set to the OFF position. Do a voltage check to make sure that the
electrical power is disconnected from the system. Secure against
resetting.
Make sure that personnel cannot be crushed or get stuck while moving
the parts of the Charge Pole.
Make sure that personnel cannot be falling from the platform when
working at height.
Warranty
Damage due to moving the Charge Pole to its position is not covered by
the warranty.
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022