5.15.2.

Pantograph setting range adjustment

1.
Determine how many cover plates (B) should be removed around the pantograph (C). If
no cover plates need be removed, go to step 5.
2.
Remove on both side the U-profiles (A) by detaching the two M6 bolts.
3.
Remove the cover plates (B) by detaching the M6 bolts.
4.
Put the cover plates, U-profiles and bolts in a safe location as it will be installed again later
on.
When the cover plates (B) are removed, the bolts for moving the pantograph is accessible
from below.
5.
The pantograph is suspended in the C-profile of the frame (G) by two suspended-plates
(with slide bearings) (F) on each side of the pantograph. The pantograph is locked by
clamping plates (E) on each side of the C-profile frame (G). From below, the lock can be
loosened by loosening the M12 bolts (D) (4x).