Make sure that the sense wires are placed back on the DC contactor
connectors. If this is not the case, then the system will not function.
13. Tighten the nuts (C) with a tightening torque of 22 ft-lb.
14. Place the protection cover back on the DC contactors.
15. Hand tighten the screws of the protection cover.
16. Tighten the cable gland's nut to secure the DC power cables.
5.16.7.

Connect the DC- power input cables in Junction Box

Preconditions:
Tools: wire cutter, wire stripper pliers, cable lugs (3x), spanner (size18), torque wrench
(size 18), cross-head screwdriver.
1.
Loosen the screws (C) (6x) of the Junction Box (A).
2.
Remove the cover (B) from the Junction Box (A).
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022
HVC‐PD E‐Bus Charger Installation Guide 
NOTICE
Page 109 of 146

Advertisement

Table of Contents
loading

Table of Contents