ABB HVC-PD Installation Manual page 47

Hide thumbs Also See for HVC-PD:
Table of Contents

Advertisement

Ensure the concrete base plate is exact perpendicular to the road (or
charging position of the bus).
Never hoist on the thread end on top the foundation block, only use the
hoisting points as indicated.
4.
Installing the counter weights
Preconditions:
2x WLL 1.5/2.5 tons lifting claws (are not delivered by ABB, use for example Starcon Universal
Lifting Claws, art.no. 99.11590081B).
With the concrete base plate in position the counter weights can be installed. These counter
weights are needed to keep the charging pole construction up right during extreme weather
conditions and to prevent the construction from tilting.
There are two bullet head anchors (2.5 K170D DH) pouring in the counter weights. Hoist the
counter weights one by one by using two lifting claws connected to two slings or chains with
sufficient capacity. The weight is 2130 kg and the foot print is 94.49 x 37.80 Inch.
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022
HVC‐PD E‐Bus Charger Installation Guide 
NOTICE
Page 47 of 146

Advertisement

Table of Contents
loading

Table of Contents