3.
Loosen and remove the cable gland's (#03 - #05) nuts for the DC power cables.
4.
Slide the cable gland's nuts over the DC power cables.
5.
Strip the insulation on the required length specified by the used lug from the end of the
DC power cables.
6.
Insert the DC- input power cable(s) into the cable gland (#03, #04 and #05, see picture
above).
7.
Attach cable lug (C) at the end of the wires (D).
8.
Remove the M12 bolts, washers and nuts from the bus-bar (G).
9.
Fit the bolt (E) with flat washer (F) and the wire (D) (6x).
10. Insert the bolt fitted with the wire into the bus-bar (G) (6x).
11. Secure the bolt (E) onto the bus-bar (G) with the spring washer (H) and the nut (I) (6x).
12. Tighten the bolts (E) and nuts (I) with a tightening torque of 59 ft-lb.
13. Tighten the cable gland's nut to secure the DC power cables.
15. Place the cover (B) back onto the Junction Box (A).
If the GND braided wire between the cover and cabinet is disconnected
during the installation of the DC- power cables, make sure that the GND
braided wire of the cover is electrically connected to the cabinet.
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022
HVC‐PD E‐Bus Charger Installation Guide 
WARNING
Page 110 of 146

Advertisement

Table of Contents
loading

Table of Contents