5.15.4.

Pantograph X-axis angel adjustment

The pantograph can be adjust at respect to the slope of the road in sideway direction (X-axis)
between -6.0º to 6.0º in steps of 1.5º, see also section Maximum slope of the road in X-axis
on Page 34.
1.
Remove the M8 bolts (A) on each side of the suspension (4x).
2.
Put the bolts (A) in a safe location as it will be installed again later on.
3.
Rotate the pantograph to the correct angle position.
4.
Install the M8 bolts in the new angle position slots.
5.
Tighten M8 bolts (A) (4x).
5.16.

Installation of the cables inside Charge Post

Make sure that the main switch of the power supply group for the product
is set to the OFF position. Do a voltage check to make sure that the
electrical power is disconnected from the system. Secure against
resetting.
5.16.1.

Open the door and remove cover plate

Preconditions:
Key that was removed from the Charge Pole.
A minimum of two persons is required.
Tool: torx screwdriver (size 2163TX-T30).
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022
HVC‐PD E‐Bus Charger Installation Guide 
DANGER
Page 103 of 146

Advertisement

Table of Contents
loading

Table of Contents