3.
Remove the DC contactor's protection cover.
4.
Loosen and remove the cable gland's (#14, #15 and #20) nuts, including the cover caps
inside the gland, for the DC+ power cables.
5.
Slide the cable gland's nuts over the DC power cables.
6.
Strip the insulation on the required length specified by the used lug from the end of the
wire (B).
7.
Insert the DC+ power cables into the right cable gland (#14, #15 and #20, see picture
above and section Gland layout of the ACS Control Module on Page 106).
8.
Attach cable lug (A) at the end of the wires.
9.
Remove the nuts and washers (C) from the bolts of the DC contactor connectors.
10. If present: remove the sense wires from the bolts of the DC contactor connectors.
11. Insert the wires (B) onto the correct bolts of the DC contactor connectors, see picture
above for the correct connection.
12. Insert the sense wires back onto the bolts of the DC contactor connectors.