Switching On The Device For The First Time; General Information Before Switching On The Device; Switching On The Device - B&R Panel PC 2100 User Manual

Hide thumbs Also See for Panel PC 2100:
Table of Contents

Advertisement

3.4 Switching on the device for the first time

3.4.1 General information before switching on the device

Checklist
The following items must be checked before the device is put into service for the first time:
• Have the installation notes specified in
• Have the permissible environmental conditions for the device been taken into account?
• Is the power supply connected correctly, and have the values been checked?
• Is the ground cable connected correctly to the ground connection?
• The device must first be put into service before additional hardware is installed.
Caution!
Before the device is put into service, it must slowly be acclimated to room temperature! Subjecting it
to thermal radiation is not permitted.
If transported at low temperatures or if there are large temperature fluctuations, the device is not per-
mitted to be subjected to any type of moisture.
Moisture can cause short circuits in the electrical circuits and damages the device.
Requirements
The following requirements must be met before switching on the device for the first time:
• The functional ground connections are as short as possible and connected to the central grounding point
using the largest possible wire cross section.
• All connection cables are connected correctly.
• A USB keyboard and USB mouse are connected (optional).

3.4.2 Switching on the device

Procedure
1. Connect and switch on the power supply.
2. The device is in service and booting; LED "Power" is lit.
Panel PC 2100 user's manual V1.17
"Installation" on page 210
been observed?
Commissioning
225

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Mappc2100-eng

Table of Contents