118 Commissioning
8
Commissioning
This section shows a step-by-step procedure for starting up exemplarily a WAGO
fieldbus node.
Exemplary Example!
This description is exemplary and is limited here to the execution of a local start-
up of one individual fieldbus node with a non-interlaced computer running
Windows.
For start-up, three steps are necessary. The description of these work steps can
be found in the corresponding following sections:
•
Connecting Client PC and Fieldbus Nodes
•
Load XML-File in the Master
•
Testing the Function of the EtherCAT
8.1
Connecting Client PC and Fieldbus Nodes
1. Mount the fieldbus node on the TS 35 carrier rail.
Follow the mounting instructions found in the "Mounting" section.
2. Connect the 24 V power supply to the supply terminals.
3. Connect the PC's ETHERNET interface to the fieldbus coupler's ETHERNET
interface (RJ-45).
4. Turn the operating voltage on.
The fieldbus coupler is initialized. The coupler determines the I/O module
configuration and creates a process image.
During start-up, the I/O LED (red) flashes.
If the I/O LED lights up green after a brief period, the fieldbus coupler is
operational.
8.2
Load XML-File in the Master
1.
Download the EtherCAT
EtherCAT
Manual
Version 1.2.1
750-354/000-001 EtherCAT® Fieldbus Coupler, ID Switch
device description file (XML file) for the
fieldbus coupler from WAGO's homepage on the Internet.
WAGO-I/O-SYSTEM 750
®
Fieldbus Node