A.6 Safety Checklist
Use this checklist to ensure that the safety requirements have been addressed.
Safety Checklist
Considerations
Is there an
emergency
power shut off?
Is there a fire
protection system
in the data center
room?
Is the computer
room adequately
equipped to
extinguish a fire?
Is antistatic
flooring installed?
Is the area below
the raised floor
free of obstacles
and blockages?
Related Topics:
•
Temperature and Humidity Requirements
A.7 Logistics Checklist
Use this checklist to ensure that the logistics requirements have been addressed.
Logistics
Checklist
Considerations
Is contact
information for
the data center
personnel
available?
Yes
See Also:
"Powering On and Off Oracle Exadata Rack" in the Oracle Exadata Database
Machine Maintenance Guide
Yes
No
N/A
(page 1-44)
No
N/A
Appendix A
Safety Checklist
Comment
Comment
A-11
Need help?
Do you have a question about the EXADATA X6-2 and is the answer not in the manual?
Questions and answers