0B-4 Maintenance and Lubrication:

Exhaust Pipe Bolt and Muffler Bolt Inspection

Tighten exhaust pipe bolts, muffler bolt and nut
Initially at 200 km (100 miles, 1 month) and every 1
000 km (600 miles, 3 months) thereafter
Check the exhaust pipe bolts, muffler bolts and nut to the
specified torque. Refer to "Exhaust Pipe / Muffler
Removal and Installation in Section 1K (Page 1K-2)".
Tightening torque
Exhaust pipe nut (a): 23 N·m (2.3 kgf-m, 16.5 lbf-ft)
Muffler mounting bolt (b): 23 N·m (2.3 kgf-m, 16.5
lbf-ft)
Muffler connecting bolt (c): 23 N·m (2.3 kgf-m, 16.5
lbf-ft)

Valve Clearance Inspection and Adjustment

B931G20206002
Inspect valve clearance
Initially at 200 km (100 miles, 1 month) and every 2
000 km (1 200 miles, 6 months) thereafter
Inspection
Valve clearance adjustment must be checked and
adjusted, a) at the time of periodic inspection, b) when
the valve mechanism is serviced, and c) when the
camshafts are removed for servicing.
1) Remove the front inner fender (LH & RH). Refer to
"Front Side Exterior Parts Removal and Installation
in Section 9D (Page 9D-6)".
2) Remove the inlet V-belt cooling duct. Refer to "V-belt
Cooling Duct Removal and Installation in Section 5A
(Page 5A-5)".
3) Remove the left side cover (1) and engine side cover
(2).
(a)
4) Remove the recoil starter (3).
(c)
(b)
I831G1020005-02
B931G20206003
1
2
I831G1020009-02
3
I831G1020010-01