13. Install all removed components on the new system board.
14. Do one of the following:
a. Install the air baffle.
b. Install the midplane drive cage.
15. Install the access panel.
16. Install the server into the rack.
17. Connect all peripheral cables to the server.
18. Connect each power cord to the server.
19. Connect each power cord to the power source.
20. Power up the server .
21. If removed, install the front bezel.
22. Make sure all firmware, including option cards and embedded devices, is updated to the same versions to ensure that the latest drivers
are being used.
23. Re-enter any Secure Boot keys that were previously added in the Secure Boot configuration.
24. Re-enter the server serial number and product ID, and configure the date and time settings .
Re-entering the server serial number and product ID
Re-entering the server serial number and product ID
About this task
About this task
After replacing the system board, re-enter the system serial number and product ID, and configure the date and time settings.
Procedure
Procedure
1. Access the UEFI System Utilities. During POST, press F9 F9.
2. From the System Utilities screen, select System Configuration > BIOS/Platform Configuration (RBSU) > Advanced Options > Advanced