Sun Microsystems Enterprise 250 Owner's Manual page 94

Hide thumbs Also See for Enterprise 250:
Table of Contents

Advertisement

What Next
Remove the NVRAM module from the replacement board and install it on the old
board for return to Sun Microsystems. See "How to Install the NVRAM/TOD
Module" on page 96.
Complete these tasks to transfer the components that you removed from the old
main logic board to the new board:
"How to Install the SSP Paddle Card" on page 92
"How to Install a CPU Module" on page 83
"How to Install the NVRAM/TOD Module" on page 96
"How to Install a Memory Module" on page 79
Complete this task to reassemble the system:
"How to Install the Side Access Panel" on page 33
When you are ready to restart the system, be sure to run POST and OpenBoot
Diagnostic tests to verify that the system functions correctly with the new parts you
have just installed. For additional information, see Chapter 11 "Diagnostics and
Troubleshooting" beginning on page 215.
Note – After installing the new main logic board, you must restore Remote System
Control (RSC) configuration parameters before you can use RSC. During RSC
configuration, RSC parameters are typically backed up to a hard disk drive. You
must restore those parameters to the RSC SEEPROM on the new main logic board.
For additional details, see the Remote System Control (RSC) User's Guide.
76
Sun Enterprise 250 Server Owner's Guide • June 1998