Figure 5-10 Removing an air filter
Step 2 Clear foreign matter inside the ventilation vent using the brush.
Step 3 Install the spare air filter.
----End
Follow-up Procedure
Dispose of the removed air filter that is confirmed faulty.

5.2.6 Replacing a Thermal Insulation Layer

Prerequisites
Impact on the System
None
Preparations
Tools: utility knife, glue for installing thermal insulation foam, tinfoil adhesive, brush,
protective gloves
Materials: thermal insulation foam, dry rag
Documents required: none
Skill requirement: cooling engineer
Procedure
Step 1 (Optional) Open the aisle floor.
Step 2 Remove the thermal insulation foam from a pipe.
Step 3 Wipe off the condensate water from the surface of the pipe.
Issue 01 (2016-01-10)
A thermal insulation layer needs to be replaced.
A spare thermal insulation layer of the same model is available and functional.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Parts Replacement
89

Advertisement

Table of Contents
loading

Table of Contents