6.1 Emergency Operations for Mains Failure

Prerequisites
The mains supply to the IDS1000 is faulty.
Context
The IDS1000 power supply and distribution system supports the following power supply
modes:
Procedure
Step 1 Check whether the UPS is working properly.
Step 2 Check whether the ATS in the mains bus coupler cabinet switches to the other mains supply
or the DG.
Issue 01 (2016-01-10)
6
One mains supply and one DG
Two mains supplies
Two mains supplies and one DG
Two mains supplies and two DGs
Perform emergency operations based on the power supply mode used by the IDS1000.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.

Emergency Operations

6 Emergency Operations
151

Advertisement

Table of Contents
loading

Table of Contents