Procedure
Step 1 Locate the water sensor to be replaced based on the alarm information on the monitoring
software terminal.
Figure 5-15 Rope-type water sensor
Step 2 Remove the signal cable and extension cable, as shown in
Figure 5-16 Removing the signal cable
Step 3 Remove the screws tightening the faulty water sensor using a Phillips screwdriver, and
remove the water sensor.
Step 4 Install a new water sensor and tighten the screws.
Step 5 Connect the signal cable and extension cable for the water sensor in reverse order of
Step 6 Check that the new water sensor is working properly.
----End
Issue 01 (2016-01-10)
For the diagram and table, see the initial configuration guide.
Figure 5-15
Dip the water detection cable into water. If the monitoring software terminal generates an alarm, the
water sensor is working properly.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
shows a rope-type water sensor.
5 Parts Replacement
Figure
5-16.
Step
2.
96

Advertisement

Table of Contents
loading

Table of Contents