Before conducting quarterly maintenance for the fire extinguishing system, notify the
related administrative departments that the fire extinguishing system will stop work during
the maintenance. In addition, disable the logical control function of the area or system to
prevent false alarms.
Before maintaining the system, ensure that all control cables to electromagnetic valve
drivers have been disconnected. This prevents the agent release due to misoperations, and
prevents accidental damage. After the maintenance is complete, reconnect the
electromagnetic valves and notify the administrative departments that the fire
extinguishing system has become operational.
Table 3-12 Quarterly maintenance checklist for the fire extinguishing system
Item
Fire control
panel
battery
Fire alarm
bell
Issue 01 (2016-01-10)
Method
Expected
Result
1. Disconnect the
The fire
AC power
control panel
when both the
reports a main
DC and AC
power supply
power supplies
fault.
are normal, and
use batteries to
supply power to
the fire control
panel.
2. Reconnect the
AC power
when the
battery voltage
drops to 23 V
DC.
Simulate a scenario
The alarm bell
to trigger the
rings loud and
smoke or heat
clear.
detector.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Maintenance
Troubleshooting
If the battery cannot be charged,
replace by following instructions in
the Installing Fire Control Panel
Batteries section in the solution
installation guide.
1. Check and reconnect cables to
the fire alarm bell.
2. If the fault persists, replace by
following instructions in
Replacing a
Buzzer.