Parts Replacement; Replacing Power Supply And Distribution System Components; Replacing A Pd510 - Huawei IDS1000-A Maintenance Manual

Air-cooled container data center
Table of Contents

Advertisement

IDS1000-A Air-Cooled Container Data Center
All-in-One Maintenance Guide
5.1 Replacing Power Supply and Distribution System
Components

5.1.1 Replacing a PD510

Prerequisites
If the condition allows, switch off the upper-level circuit breaker of the PD510 electricity
meter to be replaced.
Impact on the System
Certain services in the IDS1000 are interrupted.
Preparations
Tools: Phillips screwdriver, protective gloves
Material: spare PD510 electricity meter
Documents required: documents delivered with the PD510 electricity meter, initial
configuration table for the PD510 electricity meter
Skill requirement: power distribution system engineer
Issue 01 (2016-01-10)
A PD510 electricity meter needs to be replaced.
A spare PD510 electricity meter of the same model is available and functional.
For the table, see the initial configuration guide.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5

Parts Replacement

5 Parts Replacement
74