IDS1000-A Air-Cooled Container Data Center
All-in-One Maintenance Guide
Preparations
Tools: Phillips screwdriver, protective gloves
Materials: spare VESDA power box battery, key to the VESDA power box door
Documents required: fire extinguishing device layout diagram
Skill requirement: fire extinguishing engineer
Procedure
Step 1 Move the VESDA power box battery to the position indicated on the fire extinguishing device
layout diagram.
Step 2 Open the power box using a key, as shown in
Figure 5-60 VESDA power box
Step 3 Remove cables from the faulty VESDA battery.
Step 4 Remove the faulty VESDA battery using a Phillips screwdriver, and install the spare VESDA
battery into the power box.
Step 5 Connect battery cables.
Distinguish between the positive and negative battery terminals when connecting battery
cables.
----End
Issue 01 (2016-01-10)
For the diagram, see the initial configuration guide.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
5-60.
5 Parts Replacement
146

Advertisement

Table of Contents
loading

Table of Contents