Huawei LUNA2000-200KWH-2H1 Quick Manual
Hide thumbs Also See for LUNA2000-200KWH-2H1:

Advertisement

Quick Links

Commercial and Industrial Microgrid Energy
Storage Solution
Quick Guide (With Third-Party
Microgrid Central Controller)
Issue
04
Date
2023-12-18
HUAWEI DIGITAL POWER TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading

Summary of Contents for Huawei LUNA2000-200KWH-2H1

  • Page 1 Commercial and Industrial Microgrid Energy Storage Solution Quick Guide (With Third-Party Microgrid Central Controller) Issue Date 2023-12-18 HUAWEI DIGITAL POWER TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei Digital Power Technologies Co., Ltd. and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    Indicates a hazard with a medium level of risk which, if not avoided, could result in death or serious injury. Indicates a hazard with a low level of risk which, if not avoided, could result in minor or moderate injury. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 4 4.2.2 Preparations Before Deployment. Updated 4.2.3 Commissioning Using the Deployment Wizard. Updated 5 System Operations. Updated 6 On/Off-Grid Switching. Added D Digital Power Customer Service. Added E Contact Information. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 5 4.2.3 Commissioning Using the Deployment Wizard. Added B ESS Software Upgrade Solution for the Off-Grid PV+ESS System. Issue 01 (2023-06-05) This issue is used for first office application (FOA). Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 6: Table Of Contents

    B ESS Software Upgrade Solution for the Off-Grid PV+ESS System......46 C List of Alarms Affecting Topology Identification............48 D Digital Power Customer Service..................51 E Contact Information......................52 F Acronyms and Abbreviations....................54 Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 7: Solution Introduction

    5 kvar or above (5% of the PCS rated power), 5% even harmonics are allowed. When the PCS has no output fundamental wave current, loads with even harmonics cannot be connected. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 8: On/Off-Grid Pv+Ess System

    Table 1-1 Components of the on/off-grid PV+ESS system Name Model/Specifications Quantity Remarks Smart String ● LUNA2000-200KWH-2H1 ≤ 20 Purchased from Energy the Company ● LUNA2000-161KWH-2H1 Storage ● LUNA2000-129KWH-2H1 System (ESS) ● LUNA2000-97KWH-1H1 Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 9 ● SUN2000-450W-P2 Depending Purchased from Optimizer on the the Company ● SUN2000-600W-P (SUN2000P) actual (optional). ● MERC-1300W-P quantity of The SUN2000P is ● MERC-1100W-P PV modules supported only by SUN2000-50KTL- Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 10 Meter at the DTSU666-HW or YDS60-80 Purchased from grid the Company connection (optional) point FusionSolar iMaster NetEco Purchased from Smart PV V600R023C00CP2101 and the Company Management later versions (optional) System (SmartPVMS) Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 11: Off-Grid Pv+Ess System

    The ESS functions as the main power supply for grid forming, and also supplies power together with the PV system to loads. When the ESS is overdischarged, the DG charges the ESS. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 12 ● LUNA2000-161KWH-2H1 Storage ● LUNA2000-129KWH-2H1 System (ESS) ● LUNA2000-97KWH-1H1 Smart Power LUNA2000-100KTL-M1 ≤ 20 Purchased from Control the Company. System (PCS) The quantity ratio of PCS to ESS is 1:1. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 13 (SACU) SmartLogger, which can be used to manage devices in an array over the web user interface (WebUI) of the SmartLogger. SmartModule SmartModule1000A01 Depending on the actual networking architecture Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 14 Hz/60 Hz ● iSitePower-M-(MAP05A1, Prepared by MAB05B1) or devices with the customer the same functions ● Power: ≥ 5 kVA ● Power backup duration ≥ 1 hour Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 15: Communication Logic

    (quantity of 10M/100M auto-sensing Ethernet ports ≥ 8). The quantities of switches and Ethernet ports are configured based on the quantities of ESSs and PCSs connected to the array. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 16 Ethernet ports are configured based on the quantities of ESSs and PCSs connected to the array. In the PCS FE ring topology, a single FE ring network supports a maximum of 15 PCSs. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 17 ESS through FE, and ESSs communicate with each other through SFP optical fiber cascading. In the ESS fiber ring topology, a single fiber ring network supports a maximum of 15 ESSs. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 18 In this scenario, the SmartACU2000D-D-06 is configured and the SmartModule needs to be configured in the SACU. This topology is recommended when the quantity of ESSs ranges from 16 to 20. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 19: O&M Methods

    NetEco current and historical running site after deployment and V600R023C status of power plants and commissioning supports intelligent alarm FusionSolar reporting, analysis, diagnosis, SmartPVMS and O&M. User Manual Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 20 App User and the SUN2000 to locally device locally Manual manage a single PCS, ESS, and ● Upgrading the software SUN2000. version of a single device locally Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 21: Installation And Cable Connection

    N·m. Use a marker to mark the nuts after the torque is verified. Installing the Install the PCS on the side of the ESS using the delivered mounting brackets (including M12 bolt assemblies). Installing the SUN2000 and SUN2000P Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 22 Otherwise, the system may fail to run properly. Installing For details about the cable connections, see communicatio Communication Logic. ns cables Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 23: Check And Preparation Before Power-On

    In an outdoor scenario, you are advised to power on the PSU within 24 hours after unpacking. If the PSU cannot be powered on in time, place it in a dry indoor environment without corrosive gas. Figure 3-1 Installing the PSU Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 24 Check whether the reading of the pressure gauge on the rack mounted fire extinguishing system is normal. Remove the communications cables between the rack mounted fire extinguishing system and the CMU. The SACU or SmartLogger WebUI shall report related alarms. ----End Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 25: System Power-On And Commissioning

    Rectify the fault before proceeding with the procedure. 4.1 Device Power-On 4.1.1 On/Off-Grid PV+ESS System Power on the on/off-grid PV+ESS system when an external power supply is available. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 26 1. Turn on the ESS power switch on the UPS UPS-ESS auxiliary side. power supply (for 2. Turn on the UPS cable inlet switch 5FCB in black start) the ESS. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 27 2FCB8, and air conditioner 2 switch 2FCB9 in sequence. e. Use a multimeter to check that the output voltage of the embedded power subrack (SK1) is 53 V±5 V. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 28: Off-Grid Pv+Ess System

    4.1.2 Off-Grid PV+ESS System Power on the off-grid PV+ESS system when the UPS can supply power, the DG is not running, and the power distribution equipment has no power supply. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 29 SmartACU2000D-D-06: Turn on the SACU input switch QF03. ● If the SmartLogger3000A is configured, turn on the power switch (if any) between the SmartLogger3000A and the UPS based on site requirements. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 30 Powering on the For details, see the documents provided by the isolation vendor. transformer Powering on the Turn on the AC switch between the PCS and the isolation transformer. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 31: Deployment Commissioning

    Step 1 Click Maintenance, choose Device Mgmt. > Connect Device, and check that the devices are connected. Figure 4-3 Checking device connection To manually add an IMD, click Add Devices and set IMD access parameters. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 32 Check whether the communications cables to the battery packs are correctly and securely connected. Delete invalid modules under Running Param. on the ESU page. Then, choose Maintenance > Device Mgmt. > Connect Device and click Auto. Search. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 33 Support-E website, go to step 5. Otherwise, go to the next step. Click Choose File, select the target software package, and click Upload. After the upload is complete, click Software Upgrade. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 34: Commissioning Using The Deployment Wizard

    Device disconnection time (choose Maintenance > Device Mgmt. > Connect Device to view Device disconnection time), and then click Search for Device to check cable connections and allocate addresses. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 35 ● After a device is added or deleted, you need to click Search for Device again in Deployment Wizard. Otherwise, the system topology will not be updated. Step 3 After the device search is complete, set the grid connection state based on site requirements. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 36 Apparent Power Baseline (kVA) You are advised to retain the default under Parameter Configuration value. Maximum Overload Active Power You are advised to retain the default (kW) under Parameter Configuration value. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 37 SmartLogger3000 User Manual . Figure 4-8 Connecting to power meters Step 5 (Optional) Connect to environment monitoring instruments (EMIs). Figure 4-9 Connecting to EMIs Step 6 Set battery control parameters. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 38 Confirm and set Detection start time to the optimal time. SmartLogger V300R023C00SPC172 and later versions support this function. Step 7 Connect to a Huawei network management system (NMS). Set related parameters by referring to "Setting Parameters for Connecting to the Management System"...
  • Page 39 Send a command on the third-party NMS (for example, adjusting the settings of Microgrid compatibility) and check whether the SmartLogger can respond properly. Step 9 Connect to third-party devices. Figure 4-13 Connecting to third-party devices Step 10 Click Finish. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 40: Checking The Phase Sequence

    Correct the wiring sequence of the PCS AC power cables. If the PCS AC power cable is a multi-core cable, you are advised to exchange L1 and L3 shown in the following figure to meet the stripping length requirement. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 41 Turn on the power switches on the AC and DC sides of the PCS. Restart the PCS. Check and ensure that no Reverse Phase Sequence on AC Side alarm is reported. ----End Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 42: System Operations

    Step 2 Send a startup command to the SUN2000, PCS, and Smart Rack Controller. Method 1 (array-level): Choose Maintenance > Connect Device, and click Method 2 (bus-level): Choose Overview > Plant Running Info., and click Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 43 ● In off-grid scenarios, it is recommended that the end-of-charge SOC and end- of-discharge SOC controlled by the EMS range from 10% to 90% to ensure that the black start function works properly. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 44 ESS" again. Starting the After the black start is successful (the SmartLogger reports SUN2000 that the black start voltage setup is complete), the MGCC starts the SUN2000. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 45: On/Off-Grid Switching

    5. The MGCC sends a command to start the SUN2000. 6. The MGCC sends a PV power scheduling command. The PV active power percentage can be set to 100%. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 46 6. The MGCC sends a command to start the ESS and PCS. 7. The MGCC sends a command to start the SUN2000. 8. The MGCC sends PV and ESS power scheduling commands. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 47: System Power-Off

    Step 2 Power off the devices: Turn off the main power switches and then the auxiliary power switches of the devices by referring to the operations of 4.1 Device Power- in the reverse order. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 48 4.1 Device Power- in the reverse order. NO TE To prevent local operations on switches during subsequent power-on, you are advised not to turn off the auxiliary power switches. ----End Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 49: A Reference Documents

    161KWH-2H1, 200KWH-2H1) Smart String ESS Maintenance Manual ● LUNA2000-(97KWH-1H1, 129KWH-2H1, 161KWH-2H1, 200KWH-2H1) Smart String ESS Quick Guide ● LUNA2000-100KTL-M1 Smart Power Control System User Manual ● LUNA2000-100KTL-M1 Smart Power Control System Quick Guide Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 50 SmartACU2000D Smart Array Controller Quick Guide (Dual Opto-Electronic Ethernet Switches) SmartLogger ● SmartLogger3000 User Manual ● SmartLogger3000 Quick Guide DTSU666-HW DTSU666-HW Smart Power Sensor Quick Guide FusionSolar app FusionSolar App User Manual Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 51 Commercial and Industrial Microgrid Energy Storage Solution Quick Guide (With Third-Party Microgrid Central Controller) A Reference Documents Device Document iMaster NetEco iMaster NetEco V600R023C00 FusionSolar SmartPVMS User Manual Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 52: B Ess Software Upgrade Solution For The Off-Grid Pv+Ess System

    Step 6 To upgrade the software on the SmartLogger WebUI, click Choose File, select the target software package, and click Upload. After the upload is complete, click Software Upgrade. Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 53 PCS is connected, upgrade the PCS. For non-first-time deployment, choose Maintenance > Device Mgmt. > Connect Device and click for batch start. Step 10 Turn on the load switch. ----End Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 54: C List Of Alarms Affecting Topology Identification

    Bus Side Overvoltage on Rack Controller 3020 Bus Side Reverse Polarity on Rack Controller 3021 Insulation Resistance of Rack Controller Abnormal 3022 Rack Controller Temperature High 3023 Battery Terminal Overtemperature on Rack Controller Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 55 Abnormal 3044 Battery Pack Overcurrent 3045 Battery Pack Temperature High 3046 Battery Pack Temperature Low 3047 Battery Pack Undervoltage 3052 External DC Auxiliary Power Supply of Rack Controller Fault Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 56 3849 Air Exhaust Malfunction 1, 2 3850 Combustible Gas Detection Malfunction 3856 Battery Fault Protection 1, 2 3858 48 V DC Auxiliary Power Supply Faulty 3859 Forced Dehumidification Started Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 57: D Digital Power Customer Service

    Commercial and Industrial Microgrid Energy Storage Solution Quick Guide (With Third-Party Microgrid Central Controller) D Digital Power Customer Service Digital Power Customer Service https://digitalpower.huawei.com/robotchat/ Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 58: E Contact Information

    To ensure faster and better services, we kindly request your assistance in providing the following information: ● Model ● Serial number (SN) ● Software version ● Alarm ID or name ● Brief description of the fault symptom Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 59 Quick Guide (With Third-Party Microgrid Central Controller) E Contact Information NO TE EU Representative Information: Huawei Technologies Hungary Kft. Add.: HU-1133 Budapest, Váci út 116-118., 1. Building, 6. floor. Email: hungary.reception@huawei.com Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 60: F Acronyms And Abbreviations

    F Acronyms and Abbreviations Acronyms and Abbreviations Central Monitoring Unit Energy Storage System Fast Ethernet MGCC Microgrid Central Controller Power Control System Power Supply Unit SACU Smart Array Controller Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 61 Commercial and Industrial Microgrid Energy Storage Solution Quick Guide (With Third-Party Microgrid Central Controller) F Acronyms and Abbreviations Small Form-factor Pluggable State of Charge State of Health Uninterruptible Power Supply Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd.

Table of Contents