Cooling System - Huawei IDS1000-A Maintenance Manual

Air-cooled container data center
Table of Contents

Advertisement

IDS1000-A Air-Cooled Container Data Center
All-in-One Maintenance Guide

Cooling System

Management System (Monitoring System)
Fire Extinguishing System
Issue 01 (2016-01-10)
Replace batteries only with the ones of the same or equivalent type. Improper battery
replacement may cause an explosion.
Assign only professional engineers to perform O&M for the cooling system.
Do not block the air exhaust and return vents of air conditioners.
Promptly put serviced units into use after the cooling system is maintained; otherwise,
equipment cannot work at optimal status.
If the number of running air conditioners in an area is less than the rated minimum
number, some loads must be powered off; otherwise, temperature inside the container
may go out of control.
For detailed configurations of the cooling system, see the initial configuration guide.
Assign only professional engineers to perform O&M for the management system.
Routine maintenance for the management system is critical for long-term stable and
efficient operation of the IDS1000 because most alarms are reported over the
management system.
Promptly handle reported alarms to prevent equipment damage or service interruption.
Check and calibrate the hydrogen detection equipment sensors half a year within the
sensor service life (less than 5 years).
For detailed initial configurations for the management system, see the initial
configuration guide for the solution in use.
Do not smoke or use open flame inside the container.
Assign only qualified engineers to perform O&M for the fire extinguishing system.
Before performing routine maintenance for the fire extinguishing system, inform the
related departments of the temporary downtime due to maintenance. In addition, disable
the logical control function of the area or system to prevent false alarms. Inform the
related departments of the system recovery after the maintenance is complete.
Take antistatic measures before removing the front panel from a VESDA; otherwise, the
VESDA may be damaged.
During fire extinguishing system commissioning, disconnect the solenoid valve, and
insert the fire cylinder safety pin to prevent agent release by mistake.