5.3.2

Basic commissioning with application classes

5.3.2.1

Starting basic commissioning

Carry out basic commissioning
Preconditions
Procedure
Proceed as follows to carry out basic commissioning:
1.
2.
3.
4.
5.
Converter with CU230P-2 Control Units
Operating Instructions, 04/2015, FW V4.7 SP3, A5E34257946B AB
• The power supply is switched on.
• The operator panel displays setpoints and actual values.
Press the ESC key.
Press one of the arrow keys until the BOP-2 displays the "SETUP" menu.
In the "SETUP" menu, press the OK key to start basic commissioning.
If you wish to restore all of the parameters to the factory setting before
the basic commissioning:
4.1.
Switch over the display using an arrow key: nO → YES
4.2.
Press the OK key.
When selecting an application class, the inverter assigns the motor
control with the appropriate default settings:
STANDARD
DYNAMIC
EXPERT
5.3 Commissioning using a BOP-2 operator panel
→ Standard Drive Control (Page 129)
→ Dynamic Drive Control (Page 131)
If you select this setting or if no application class is
listed: → Starting basic commissioning (Page 119)