5.3

Basic commissioning with IOP

Basic commissioning wizard
The Basic Commissioning wizard detailed below is for Control Units with version 4.4
software or higher.
Procedure
For performing the basic commissioning of the converter with the IOP operator panel,
proceed the following steps:
1.
2.
3.
4.
Converter with control units CU250D-2
Operating Instructions, 04/2015, FW V4.7.3, A5E34261542B AB
Select "Basic Commissioning..." from the Wizards
menu.
Select "Yes" or "No" to a factory reset.
The factory reset is performed prior to saving all the
parameter changes that have been made during the
basic commissioning process.
Select the Control Mode for the attached motor.
Select the correct Motor Data for your Inverter and at-
tached motor.
This data is used to calulate the correct speed and dis-
played values for the application.