4. Switch on the motor.
The inverter starts the motor data identification. This measurement can take several
minutes. After the measurement, the inverter switches off the motor.
5. Relinquish the master control after the motor data identification.
6. Press button
You have completed the motor data identification.
Procedure with Startdrive
To initiate motor data identification and optimize the motor control, proceed as follows:
1. Open the control panel.
2. Assume master control for the inverter.
3. Set the "Drive enables"
4. Switch on the motor.
The inverter starts the motor data identification. This measurement can take several
minutes. After the measurement, the inverter switches off the motor.
5. Relinquish the master control after the motor data identification.
6. Save the settings in the inverter (RAM → EEPROM):
You have completed the motor data identification.
Self-optimization of the speed control
If you have selected not only motor data identification but also rotating measurement with
self-optimization of the speed control, you must switch on the motor again as described
above and wait for the optimization run to finish.
Converter with CU230P-2 Control Units
Operating Instructions, 04/2015, FW V4.7 SP3, A5E34257946B AB
(RAM to ROM).
Commissioning
5.4 Commissioning with a PC