4.6 Remove / mount pluggable bridges for additional terminals

4.6
Remove / mount pluggable bridges for additional terminals
4.6
Introduction
The additional terminal is equipped with 3 pluggable bridges from factory.
With the 3 plugged bridges, all terminals on the additional terminal have the same potential.
If additional potentials are required, various potentials can be achieved by removing the
pluggable bridges. Detailed information pertaining to the expansion of voltage groups can be
found in the device manual in the chapter entitled
TE-U120S4x10 and TE-U120C4x10 (6ES7193-4FLx0-0AA0)
Requirements
• The DIN rail is installed.
Required tools
3-mm screwdriver
Remove pluggable bridges
1. Remove the labels from the additional terminals.
2. Insert the screwdriver from the side, underneath the pluggable bridge that is to be
3. Loosen the bridge and pull the bridge out.
4. If necessary, repeat steps 2 and 3.
5. Replace the labeling strips.
4-14
removed.
Terminal modules > Additional terminals
.