Optical Transmission Test (Oc-192, Oc-48, Oc-12, Oc-3) - Alcatel-Lucent 1850 TSS-60 Installation And System Turn-Up Manual

Transport service switch
Table of Contents

Advertisement

Connecting adjacent network elements
............................................................................................................................................................................................................................................................

Optical transmission test (OC-192, OC-48, OC-12, OC-3)

Procedure
Proceed as follows:
........................................................................................................................................................................................................................
1
Use the
........................................................................................................................................................................................................................
2
Click on the
........................................................................................................................................................................................................................
3
Yes
Click
........................................................................................................................................................................................................................
4
Wait 15 minutes.
........................................................................................................................................................................................................................
5
At the test location, enter the following GUI command:
Performance -> View PM Reports -> OCn Line
........................................................................................................................................................................................................................
6
Double-click
........................................................................................................................................................................................................................
7
Select
........................................................................................................................................................................................................................
8
Time Period
For
........................................................................................................................................................................................................................
9
Monitored Date,
For
........................................................................................................................................................................................................................
10
Monitor Time
For
........................................................................................................................................................................................................................
11
Monitor Level
For
........................................................................................................................................................................................................................
12
Under the
............................................................................................................................................................................................................................................................
365-372-603R2.0
Issue 1 January 2009
GUI
Performance -> Initialize PM Registers.
command:
Both
.
to execution command.
CP main-1
.
Port 1 (OC3)
.
1 Day.
select
Current Date.
select
All.
Select
0-UP.
Select
Near End
tab click on the
Optical transmission test (OC-192, OC-48, OC-12, OC-3)
Select All
button.
7 - 1 1