Table 16
Prepare for upgrade steps (Part 2 of 2)
Procedure Step
Connecting a terminal
Printing site data
Performing a template audit
Backing up the CP PII or CP PIV customer database
Planning
Planning for an upgrade involves the following tasks:
Read and understand the current release Product Bulletin.
Conduct a site inspection to determine proper power and grounding.
Review the site profile to determine proper foot space if adding new
columns or modules.
Identify all applications (CallPilot, SCCS, IP, etc.) that are currently
installed on the source platform.
Identify and correct outstanding service problems.
Verify the site log is updated with current trunking, call routing,
application notes, and site contact information.
Review all product bulletins and alerts that impact the site.
Download a copy of the customer database media converter tool. This
tool is used to transfer the customer database from floppy disk to CF card
if you are upgrading from a CP PII.
Prepare a contingency plan for backing out of the upgrade.
Avaya Communication Server 1000E Upgrade
Upgrading a CP PII or CP PIV to CP PM
DANGER OF ELECTRIC SHOCK
In a DC-powered system, power to the column can
remain on during the following procedures. In an
AC-powered system, however, power to the entire
column must be shut down throughout the procedures.
Page 131 of 226
Hardware Upgrade Procedures