Reinstalling the Standard Cable Manager After Installing an MX960 Router with a Lift
Copyright © 2017, Juniper Networks, Inc.

Figure 68: Reinstalling an FPC

To reinstall the standard cable manager (see
Attach an ESD grounding strap to your bare wrist and connect the strap to one of the
1.
ESD points on the chassis.
Position the cable manager on the studs on the lower front of the chassis.
2.
Insert the nuts on the corners in the cable manager onto the studs on the chassis.
3.
Using a 7/16-in. (11 mm) nut driver, tighten the nuts securely.
4.
Chapter 16: Installing the MX960 Router
Figure 69 on page
224):
223