7. Fieldbus Device Commissioning

This section outlines a typical process to follow to commission a fieldbus loop in an
Experion system. This section does not provide detailed procedures for each stage in the
process. Please reference appropriate sections in this document or applicable vendor
documentation for detailed information, if required.
The following table lists the topics included in this section. If you are viewing this
information online, just click the topic title to jump to the information location.

Getting Started

Connecting Devices
Checking Device
Checking Control Strategy
Flowchart Summary
7.1
Getting Started

Read this first

The CIOM-A Fieldbus Interface Module (FIM) sets many parameters within a fieldbus
device during its initial setup and commissioning in an Experion system. While you can
change some parameters, such as calibration ones, when the device is being operated on a
workbench or at a location apart from the system, you must not change certain other
parameters. The following table outlines the functions you must consider before
commissioning a device.
For This Function. . .
R400
Experion PKS Series A Fieldbus Interface Module User's Guide
July 2010
Topic
Consider This . . .
Honeywell
277

Advertisement

Table of Contents
loading

This manual is also suitable for:

Experion pks series a

Table of Contents