Appendix 2 Application Practice

Here, we practice the continuous positioning, teaching/teaching playback and fixed-feed/
fixed-feed stepping.
Start the practice after writing the project "SCHOOL_(positioning)" to the PLC. For the steps
to the practical training, refer to Chapter 6 "Practice (2) Training in Positioning Control."
If this training is performed after practice in advanced synchronous control (refer to Chapter
7), perform the home position return (refer to Section 6.8.3), and delete the project
"SCHOOL_(advanced)" in accordance with the following procedure.
(1) Click [Online] → [Read from PLC] on GX Works3
Click!
(2) An Online Data Operation dialog box appears.
Click!
Go to next page
App-17
menu.
Click the [Delete] tab.