4.5.8 Zero Gas Xducrs

Instructions
Zero Gas Xducrs menu
4-26
The Zero Gas Xducers instructions appear when the focus is on the Zero Gas
Xducer menu item.
Read all steps before you start:
1. Remove all cylinders.
2. Disconnect all pipeline supplies.
3. Select Zero Gas Xducrs.
4. Select Start Zero on the next menu.
This page also shows:
Gas supply counts
Gas supply ID
A failed test is usually the result of a pipeline or cylinder still connected to the
system.
• If the outcome of the calibration is Pass, the new calibration data is saved.
• If the outcome is Fail, the old calibration data is retained.
• The result of the calibration is saved to the Event Log.
Selecting Previous Menu before the calibration is done aborts the calibration
in progress and keep the old calibration constants.
The Zero Gas Xducrs menu shows only transducers that are installed.
If not installed, the menu row is blank.
Menu Item
Message text
O2 Pipeline
O2 Cylinder 1
O2 Cylinder 2
N2O Pipeline
N2O Cylinder
Air Pipeline
Air Cylinder
Start Zero
Disconnect all pipelines and
remove cylinders. Then select
Start Zero.
Previous Menu
Return to the previous menu.
During Calibration:
"Calibration in progress. Push
ComWheel to cancel."
Values
0-4095 Counts
0-4095 Counts
0-4095 Counts
0-4095 Counts
0-4095 Counts
0-4095 Counts
0-4095 Counts
04/08 M1046983

Advertisement

Table of Contents
loading

Table of Contents