1st pass to 30 N-m (22 ft-lb)
2nd pass to 50 N-m (37 ft-lb)
3rd pass to 70 N-m (51 ft-lb)
CD466
5. Install the valve buckets with shims in the locations
from which they were previously removed; then
install the camshafts (see REMOVING AND
INSTALLING CAMSHAFTS/VALVE BUCKETS
in this section).
NOTE: It is highly recommended to check valve
clearance on all valves after disassembly; however, if
any valves or valve seats were replaced or ground,
valve clearance MUST be checked on the appropriate
valves and adjusted as specified (see ADJUSTING
VALVE CLEARANCE in this section).
6. Install the camshaft drive belt and covers (see
REMOVING AND INSTALLING CAMSHAFT
DRIVE BELT in this section).
7. Connect the exhaust pipe to the exhaust manifold
and secure with the cap screws and nuts tightened
securely.
MOD549
8. Install the fuel rail and injectors and secure with the
two cap screws. Tighten to specifications.
MF135A
9. Install the air inlet tube to the throttle body and
tighten the clamp securely; then insert the throttle
control connector (6) into the receptacle in the throt-
tle body and seat securely.
MF134A
10. Connect the three fuel injector connectors (7) to the
fuel injectors; then connect the IAT/MAP connector
(5) to the sensor on the manifold.
MF144A
11. Install the fuel hose connector onto the fuel rail; then
install the P-clamp holding the fuel line to the intake
manifold; then install the coil pack onto the cylinder
head and secure with the two cap screws and new
lock nut. Tighten securely.
83